Skip to main content
File #: 25-0867    Version: 1 Name:
Type: CM Action Item - Open & Responsible Government Status: Passed
File created: 7/10/2025 In control: Board of Commissioners
On agenda: 11/19/2025 Final action: 11/19/2025
Title: Request approval to renew existing contracts - Department of Information Technology, 23ITB140062B -PS, Cabling and Physical Security in a total amount not to exceed $6,975,000.00 with (A) GC&E Systems Group, Inc. (Norcross, GA) in an amount not to exceed $2,475,000.00; and (B) NetPlanner Systems, Inc. (Peachtree Corners, GA) in an amount not to exceed $4,500,000.00 to provide countywide structured cabling services. This action exercises the second of two renewal options. No renewal options remain. Effective dates: January 1, 2026, through December 31, 2026. (APPROVED)
Attachments: 1. Exhibit 1: Contract Renewal Agreement - GC&E, 2. Exhibit 1: Contract Renewal Agreement - NetPlanner Systems, Inc., 3. Exhibit 2: Contract Renewal Evaluation Form - GC&E, 4. Exhibit 2: Contract Renewal Evaluation Form - NetPlanner Systems, Inc., 5. Countywide Structured Cabling and Physical Security - FY26 Proposed Project List 082525

 

Department

Information Technology

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval to renew existing contracts - Department of Information Technology, 23ITB140062B -PS, Cabling and Physical Security in a total amount not to exceed $6,975,000.00 with (A) GC&E Systems Group, Inc. (Norcross, GA) in an amount not to exceed $2,475,000.00; and (B) NetPlanner Systems, Inc. (Peachtree Corners, GA) in an amount not to exceed $4,500,000.00 to provide countywide structured cabling services. This action exercises the second of two renewal options. No renewal options remain. Effective dates: January 1, 2026, through December 31, 2026.  (APPROVED)

 

body

Requirement for Board Action (Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-394(6), the Purchasing Department shall present all renewal requests to the Board of Commissioners at least 90 days prior to the contract renewal date or 60 days if the contract term is six (6) months or less.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Open and Responsible Government

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background: This contract will provide the county with cabling products and services to meet the requirements as delineated within the Scope of Work. The County has explicit requirements encompassing Structured Cabling and Physical Security services to support operational and capital projects to include day-to-day departmental requirements and ongoing requirements to facilitate moves, additions, and changes to its voice, data, video surveillance and card access control infrastructure components. We adopted a multi-vendor strategy to heighten value for Fulton County by reducing the risk of single-vendor dependencies (capability or capacity) and spur competition.

 

Scope of Work:  Providing products and services supporting Fulton County Structured Cabling and Physical Security (Access Control and Video Surveillance) Infrastructure. Providing products for the installation and maintenance of Fulton County main distribution frames (MDF's), intermediate distribution frames (IDF's), Data Center, and other cable distribution requirements. This includes installation of inside and outside plant structured cabling as well as associated equipment and services to support the cabling and its operability. The installations will comprise of Voice, Data, Video Surveillance and Physical Access Control System cabling infrastructures. Cabling types will consist of copper, fiber, low and high voltage electrical to include new buildings and renovations, as well as additions to and repair of existing cabling systems. Products and services will be provided by the selected vendor, on demand, and as determined by Fulton County.  

 

Community Impact: The approval of this item will allow community projects within the county's public facilities to continue as scheduled. Provide cabling and physical security infrastructure supporting technology and safety contributing to the quality of life for both individuals and groups in the community

 

Department Recommendation: The Department of Information and Technology recommends approval.

 

Project Implications: If the Board action is not approved the County will not be able to continue with operational and capital projects within county buildings and Infrastructure improvement plans without a valid cabling contract.

 

Community Issues/Concerns: There are no community concerns with this item.

 

Department Issues/Concerns: The Countywide Structured Cabling and Physical Security contract is essential to FCIT to ensure consistency, standardization, and quality of structured cabling physical security infrastructures throughout facilities all over the County.

 

Contract Modification

 

  GC&E Systems Group, Inc.

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

24-0201

3/20/2024

$4,528,095.00

1st Renewal

24-0830

12/4/2024

$4,528,095.00

2nd Renewal

 

 

$2,475,000.00

Total Revised Amount

 

 

$11,531,190.00

 NetPlanner Systems, Inc.

 

 

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

24-0201

3/20/2024

$2,438,205.00

1st Renewal

24-0830

12/4/2024

$2,446,905.00

2nd Renewal

 

 

$4,500,000.00

Total Revised Amount

 

 

$9,385,110.00

 

 

 

 

 

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value: $6,975,000.00

 

(A)

Contract Value:                                           $2,475,000.00

Prime Vendor:                                           GC&E systems Group, Inc. 

Prime Status:                                           Native American Male Business Enterprise

Location:                                                                Peachtree Corners, GA 

County:                                                                Gwinnett County

Prime Value:                                           $1,930,500.00 or 78.00%

 

Subcontractor:                                           Divine Solutions 
Subcontractor Status:                      African American Male Business Enterprise   

Location:                                                                Stone Mountain, GA

County:                                                                DeKalb County

Contract Value:                                           $297,000.00 or 12.00%

 

Subcontractor:                                           Shiflett Enterprise, Inc.

Subcontractor Status:                      White Female Business Enterprise 

Location:                                                                Newman, GA

County:                                                                Coweta County

Contract Value:                                           $247,500.00 or 10.00%

 

Total Contract Value:                      $2,475,000.00 or 100.00%

Total Certified Value:                     $2,475,000.00 or 100.00%

 

(B)

Contract Value:                                           $4,500,000.00

Prime Vendor:                                           Net Planner 

Prime Status:                                           Non-Minority 

Location:                                                                Peachtree Corners, GA

County:                                                                Gwinnett County

 

Prime Value:                                           $3,037,500.00 , 67.50%

(JV 70/30% - Integrated Communication Network, Inc - 

AAMBE $911,250.00)

 

Subcontractor:                                           Integrated Communication Network, Inc

Subcontractor Status:                      African American Male Business Enterprise  

Location:                                                                Stonecrest, GA

County:                                                               DeKalb County

Contract Value:                                           $1,350,000.00 or 30.00%

 

Subcontractor:                                           5 Points Electrical, Inc.

Subcontractor Status:                      Asian American Male Business Enterprise  

Location:                                                                Norcross, GA

County:                                                                Gwinnett County

Contract Value:                                           $112,500.00 or 2.50%

 

Total Contract Value:                      $4,500,000.00 or 100.00%

Total Certified Value:                      $2,373,750.00 or 52.75%

Grand Contract Total:                      $6,975,000.00 or 100.00%

Grand Certified Value:                      $4,848,750.00 or 69.52%                                          

 

Exhibits Attached

Exhibit 1: Contract Renewal Agreements

Exhibit 2: Contract Renewal Evaluations Forms

Exhibit 3: Performance Evaluations

Exhibit 4: Project List Proposal

 

Contact Information
title

Kevin Kerrigan, Chief Information Officer, Information Technology - 404-612-0057

 

Contract Attached
title

No


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$6,966,300.00

Previous Adjustments:

$6,975,000.00

This Request:

$6,975,000.00

TOTAL:

$20,916,300.00


Fiscal Impact / Funding Source

Funding Line 1:

Funding provided by agencies requesting products and services - $6,975,000.00

Key Contract Terms

Start Date: 1/1/2026

End Date: 12/31/2026

Cost Adjustment

Renewal/Extension Terms: No renewal options remain

Overall Contractor Performance Rating:

GC&E Systems Group, Inc.  91

NetPlanner Systems, Inc.     97

 

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

4/23/2025

7/22/2025