Department
Public Works
Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title
Request approval of a change order less than 10% - Public Works, 17RFP031617K-DJ Progressive Design/Build Services for Big Creek Water Reclamation Facility (WRF) Expansion Project Phase 2B in the amount of $201,545.00 with Archer Western-Brown and Caldwell Joint Venture (Atlanta, GA) to cover the impact of tariffs for material and equipment and to extend the contract term by eleven (11) additional days due to inclement weather so that Final Completion is now 1411 consecutive days from the issuance of the Notice to Proceed or July 5, 2024. Effective upon BOC approval. (APPROVED)
ITEM REMOVED FROM THE CONSENT AGENDA FOR SEPARATE CONSIDERATION AS REQUESTED BY COMMISSIONER ABDUR-RAHMAN
body
Requirement for Board Action (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.
Strategic Priority Area related to this item (If yes, note strategic priority area below)
Health and Human Services
Commission Districts Affected
All Districts ☐
District 1 ☐
District 2 ☒
District 3 ☐
District 4 ☐
District 5 ☐
District 6 ☐
Is this a purchasing item?
Yes
Summary & Background: This request for a change order is to address the impact to cost due to unforeseen tariffs that have been placed on construction materials. The JV team is seeking the ability to utilize the Owner’s Contingency to offset the 13% increase to value added taxes (VAT) on various materials to be used within this project. The total amount requested is $201,545.00 and will be used to offset the tariffs imposed on ductile iron pipe and other accessories. Based on the contract, the Owner’s Contingency can be used to compensate any additional costs due to inclement weather.
Additionally, this request is to extend the existing contract an additional eleven (11) days to complete the project due to inclement weather during the calendar year of 2021. Incurred overhead charges over the duration of the eleven (11) inclement weather days are detailed in attachments to this item.
Community Impact: No community issues/concerns have been noted.
Department Recommendation: The Department of Public Works recommends approval of this item.
Project Implications: The required tasks and associated project schedule to achieve substantial completion of phase 2B of the Big Creek Expansion Project are clearly defined. The 13% increase in VAT has affected negotiated price points for material and equipment related to this upgrade/expansion. This proposed action allows those concerns to be addressed thru utilization of the Owner’s Contingency/allowance.
Community Issues/Concerns: No community issues/concerns have been noted
Department Issues/Concerns: No Department Issues/Concerns noted.
Contract Modification
Current Contract History |
BOC Item |
Date |
Dollar Amount |
Original Award Amount |
20-0476 |
7/8/2020 |
$274,768,712.00 |
1st Renewal |
|
|
$.00 |
2nd Renewal |
|
|
$.00 |
Extension #1 |
22- |
5/18/2022 |
$201,545.00 |
Total Revised Amount |
|
|
$274,970,257.00 |
Contract & Compliance Information (Provide Contractor and Subcontractor details.)
Contract Value: $201,545.00
Prime Vendor: Archer Western/Brown and Caldwell (JV Partners 90/10)
Prime Status: Non-Minority
Location: Atlanta, GA
County: Fulton County
Prime Value: $201,545.00 or 100.00%
Total Contract Value: $201,545.00 or 100.00%
Total M/FBE Value: -0-
Exhibits Attached
Exhibit 1: Extension No.1 to Form of Contract
Exhibit 2: Contractor’s Performance Report
Exhibit 3: VAT Material
Contact Information (Type Name, Title, Agency and Phone)
title
David Clark, Director of Public Works, 404-612-2804
Contract Attached
title
Yes
Previous Contracts
title
Choose an item.
Total Contract Value
Original Approved Amount: |
$274,768,712.00 |
Previous Adjustments: |
$0.00 |
This Request: |
$201,545.00 |
TOTAL: |
274,970,257.00 |
Grant Information Summary
Amount Requested: |
|
☐ |
Cash |
Match Required: |
|
☐ |
In-Kind |
Start Date: |
|
☐ |
Approval to Award |
End Date: |
|
☐ |
Apply & Accept |
Match Account $: |
|
|
|
Fiscal Impact / Funding Source
Funding Line 1:
235-540-5400-S157: W&S Construction-2020, Public Works, Big Creek Plant Expansion
Key Contract Terms |
Start Date: Upon BOC Approval |
End Date: 7/5/2024 |
Cost Adjustment: |
Renewal/Extension Terms: |
Overall Contractor Performance Rating:
Would you select/recommend this vendor again?
Choose an item.
Report Period Start: |
Report Period End: |
1/1/2022 |
3/31/2022 |