Title: Request approval of Guaranteed Maximum Price (GMP) - Department Public Works, 23RFP139070K-JAJ, Progressive Design-Build Services for Campbellton Road Pump Station and Force Main in an amount not to exceed $20,332,906.00 with Sol Construction, LLC (Atlanta, GA), to perform all final design and construction activities associated with the installation of a new pump station and associated force main pipelines to serve South Fulton County. Effective upon issuance of the Notice to Proceed (NTP) with work to be completed within 24 months of the issuance of the NTP. (APPROVED)
Attachments: 1. Exhibit 1: Amendment No. 2 to Form of Contract, 2. Exhibit 2: GMP Based on 80% Design, 3. Exhibit 3: Contractor Performance Report

 

Department

Public Works

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval of Guaranteed Maximum Price (GMP) - Department Public Works, 23RFP139070K-JAJ, Progressive Design-Build Services for Campbellton Road Pump Station and Force Main in an amount not to exceed $20,332,906.00 with Sol Construction, LLC (Atlanta, GA), to perform all final design and construction activities associated with the installation of a new pump station and associated force main pipelines to serve South Fulton County. Effective upon issuance of the Notice to Proceed (NTP) with work to be completed within 24 months of the issuance of the NTP.  (APPROVED)

body


Requirement for Board Action
(Cite specific Board policy, statute or code requirement)

In accordance with the State of Georgia O.C.G.A § 36-91, Georgia Local Government Public Works Construction Law, all competitive sealed proposals (RFPs) for public works construction projects (CM at Risk, Construction PM, D/B Projects) costing $100,000.00 or more shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Health and Human Services

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background: The Campbellton Road Pump Station and its associated forcemain are facilities identified within the South Fulton Capacity Study, which was approved by the BOC under Agenda Item No. 21-0143 on February 17, 2021. Recent discussions with the City of Chattahoochee Hills and the City of South Fulton confirmed the continued need for extension of sanitary sewer services within this portion of the sewer shed in order to support the continued development of this portion of South Fulton County.  

 

Scope of Work: The Campbellton Road Pump Station and Force Main Project will construct one (1) new pump station and approximately twenty thousand linear feet (3.8 miles) of force main pipeline to serve portions of the Cities of Chattahoochee Hills and South Fulton. The new pump station and force main pipeline will direct untreated wastewater from this section of South Fulton County to existing facilities, directing that flow to the Camp Creek WRF via the Deep Creek Pump Station. The initial design of the project was awarded to the Sol Construction/Prime Engineering JV on July 10, 2024, BOC (Agenda Item No. 24-0484) under the Progressive Design-Build model. The Sol Construction / Prime Engineering JV has provided a Guaranteed Maximum Price (GMP) for the construction of the project based on the 80% design documents.  The total GMP for the project in the amount of $20,332,908 has been reviewed by Public Works staff. The $20,332,906.00 GMP includes $728,124.32 (3.4%) in contractor and owner contingencies to address unforeseen construction elements during the construction of the pump stations and installation of the force main pipeline.

 

Community Impact: This project will support the expected growth and new developments planned for the portions of the cities of Chattahoochee Hills and South Fulton near the intersection of Campbellton-Fairburn Road (SR92) and Cascade Palmetto Hwy (SR154).

 

Department Recommendation: The Public Works Department recommends approval of this item.

 

Project Implications: This project aligns with the goals and expectations presented within the South Fulton Capacity Study.

 

Community Issues/Concerns: Without approval of this Agenda Item the service areas in question will remain unsewered. This Agenda Item allows the expansion of the Fulton County sanitary sewer network within the South Fulton County area.

 

Department Issues/Concerns: The Department of Public Works has not identified any issues/concerns regarding this project.

 

Contract Modification:

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

24-0484

7/10/2024

$1,918,000.00

Amendment No. 1 (Extension)

25-0249

4/2/2025

$.00

Amendment No. 2 (GMP)

 

 

$20,332,906.00

Total Revised Amount

 

 

$22,250,906.00

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Click or tap here to enter text.

 

Exhibits Attached 

Exhibit 1: Amendment No. 2 to Form of Contract

Exhibit 2: GMP Based on 80% Design

Exhibit 3: Contractor Performance Report

 

Contact Information (Type Name, Title, Agency and Phone)
title

David E. Clark, Director, Public Works 404-612-2804

 

Contract Attached
title

No


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$1,918,000.00

Previous Adjustments:

$0.00

This Request:

$20,332,906.00

TOTAL:

$21,132,906.00


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

203-540-5400-S171, Water & Sewer R&E, Public Works, Campbellton Pump Station, 20,332,906.00.

 

Key Contract Terms

Start Date: BOC Approval

End Date: 24 months of NTP issuance

Cost Adjustment:

Renewal/Extension Terms: No renewal options


Overall Contractor Performance Rating:

Would you select/recommend this vendor again?

Yes

 

Report Period Start: