Title: Request approval of a Resolution authorizing an Easement Agreement between Fulton County, Georgia and Atlanta Gas Light Company for the purpose of relocating and upgrading service lines onsite at the Fulton County Executive Airport - Charlie Brown Field; to authorize the Chairman to execute the Easement Agreement and related documents; to authorize the County Attorney to approve the Easement Agreement and related documents as to form; and for other purposes. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
Attachments: 1. AGL Exhibit A, 2. Atlanta Gas Light Easement Agreement pjo, 3. Resolution - Atlanta Gas Light Executive Airport pjo, 4. 2024-0460
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Department

Real Estate and Asset Management

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

Request approval of a Resolution authorizing an Easement Agreement between Fulton County, Georgia and Atlanta Gas Light Company for the purpose of relocating and upgrading service lines onsite at the Fulton County Executive Airport - Charlie Brown Field; to authorize the Chairman to execute the Easement Agreement and related documents; to authorize the County Attorney to approve the Easement Agreement and related documents as to form; and for other purposes.  (APPROVED UPON ADOPTION OF THE CONSENT AGENDA) 

body

 

Requirement for Board Action (Cite specific Board policy, statute or code requirement)

Pursuant to O.C.G.A. Sec. 36-9-3, Fulton County is authorized to grant easements without a competitive process. Further, pursuant to Fulton County Code Sec. 1-117, the Board of Commissioners is vested with exclusive jurisdiction and control over all property of the County.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Open and Responsible Government

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     

 

Is this a purchasing item?

No

 

Summary & Background (First sentence includes Agency recommendation. Provide an executive summary of the action that gives an overview of the relevant details for the item.)

 

Scope of Work: Atlanta Gas Light Company (“AGL”) has submitted a request to the Department of Real Estate and Asset Management and the Department of Public Works for a replacement access easement at the Fulton County Executive Airport. The easement is needed as part of AGL’s infrastructure improvement initiative to install roskote coated lines to provide additional protection against corrosion which will increase the economic life span, and utility of its service lines.

 

Before relocating and installing roskote coated natural gas service lines, AGL’s regulations require that all new utility service line connections formally acknowledge their access rights within the specific area(s) in which their natural gas services lines are installed. The easement area to be conveyed is in Land Lots 22 and 53 of the 14th FF District of Fulton County, Georgia.

 

 

Community Impact: Approval of the Easement Agreement and related documents will ensure the stability and reliability of AGL’s utility infrastructure, reducing the likelihood of repairs to service lines and potential hazards to residents and businesses within this area.

 

Department Recommendation: The Department of Real Estate and Asset Management and the Department of Public Works recommends approval of an Easement Agreement between Fulton County and the AGL for the purpose of completing planned upgrades to their gas service lines at the Fulton County Executive Airport - Charlie Brown Field.

 

Project Implications: AGL’s proposed project will assist with their initiative to update and replace its infrastructure for the purpose of maintaining optimum efficiency and safety.

 

Community Issues/Concerns: None.

 

Department Issues/Concerns: None.

 


Fiscal Impact / Funding Source

Funding Line 1: