File #: 25-0731    Version: 1 Name:
Type: Consent - Health and Human Services Status: Agenda Ready
File created: 9/3/2025 In control: Board of Commissioners
On agenda: 10/1/2025 Final action:
Title: Request approval of a change order less than 10% - Public Works, 17RFP031617K-DJ Progressive Design/Build Services for Big Creek Water Reclamation Facility (WRF) Expansion Project Phase 2B in the amount not to exceed $4,810,722.37 to recognize a substantial completion date of August 6, 2025 and to change the final completion date to October 31,2025 with Archer Western-Brown and Caldwell Joint Venture (Atlanta, GA) to cover costs and time associated with the completion of the project. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
Attachments: 1. Extension No. 6 to Form of Contract, 2. Archer-Western CPR
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Department

Public Works

 

Requested Action

title

 

Request approval of a change order less than 10% - Public Works, 17RFP031617K-DJ Progressive Design/Build Services for Big Creek Water Reclamation Facility (WRF) Expansion Project Phase 2B in the amount not to exceed $4,810,722.37 to recognize a substantial completion date of August 6, 2025 and to change the final completion date to October 31,2025 with Archer Western-Brown and Caldwell Joint Venture (Atlanta, GA) to cover costs and time associated with the completion of the project.  Effective upon BOC approval.  (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)

body


Requirement for Board Action

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Health and Human Services

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background The current contract structure between Fulton County and the Joint Venture (JV) requires the Public Works Department to obtain BOC approval for all spending increases beyond the previously approved GMP (Guaranteed Maximum Price).  This includes use of the project’s Owner Contingency funds. Upon approval the Public Works Department will allocate these contingency funds to cover all costs associated with this action. The work that is itemized below is required to complete the project and have the facility perform as designed. 

 

Substantial Completion of the plant was achieved on August 6, 2025 and the JV is currently working to complete final punchlist items and site remediation. This BOC item represents the last request to access contingency funds the JV requires to complete this project.   

 

Scope of Work: The Public Works Department Is seeking the approval to utilize the Owner’s Contingency within the contract to address the following twenty-four (24) items:

Item

Scope of Work Description

Cost Impact

1

Temporary pipe connection PS- existing digesters.

$27,789.55

2

Sanitaire diffuser replacement.

$501,908.43

3

Additional pumping during digestor cleaning

$135,727.74

4

Time impact analyses TIA 05(digestor cleaning) 

$1,023,000.00

5

Kubota delay impact of 61 days

$122,000.00

6

EQ junction box demolition

$77,429.71

7

Weather Days 2024- Jan.1 2024-Nov. 30 2024 (10)

$201,346.40

8

Primary clarifier repair parts

$93,714.75

9

Notice of hazardous materials-Chemical bldg.

$15,495.77

10

Additional sludge removal

$166,981.61

11

Additional work required within EQ

$138,705.18

12

Odor control ductwork debris removal

$4,537.87

13

Storm pipe repairs

$120,826.21

14

Grit removal from existing BNR trains

$246,501.97

15

Building sign modifications

$6,872.76

16

Weather Days January 2025 (3)

$38,127.93

17

Digestor 1-4 work/ inspection for cracks 

$598,578.70

18

Existing blower #4 refurbishment (Gardner Denver)

$40,822.98

19

Existing air line cleaning

$4,232.16

20

Airflow Meters

$100,380.53

21

Weather Days 2025- May (5) 

$48,742.50

22

Weather Days 2025- June (2)

$22,419.91

23

Digestor blower strategy

$22,863.71

 

Subtotal of Items Completed by Contractor

$3,759,006.37

 

 

 

24

Medium voltage switchgear & ferroresance arch-flash malfunction. (Not To Exceed)

$1,051,716.00

 

Total Cost for Change Order #6 (Not To Exceed)

$4,810,722.37


These items were not included in the original GMP for the project, however, since the project has continued to be completed within budget, the remaining balance of the owner’s contingency is sufficient to cover these expenses.  All of these elements will allow for improvements to the plant’s operation and the overall safety of the facility. 

Currently the contractor has completed and is owed compensation for items #1 through #23 in the above table.  The total costs associated with item #24 are still being finalized by the Joint Venture, but they have assured Fulton County that it will not be greater than the amount shown.  Therefore, the actual change order amount paid to the Joint Venture may be less than the requested $4,810,722.17.  Any cost savings from this final change order will remain with the Big Creek project.

Community Impact: No immediate impact to the community is expected from this item.

 

Department Recommendation: The Public Works Department recommends approval of this item.

 

Project Implications: Approval of this item will enable the Joint Venture to address critical operational improvements and punch list items necessary for overall project completion.

 

Community Issues/Concerns: No Community issues/concerns have been noted.

 

Department Issues/Concerns: The Public Works Department has not identified any concerns/issues with this request. 

 

Contract Modification

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

20-0476

7/8/2020

$274,768,712.00

Change Order #1

22-0661

9/21/2022

$259,128.00

Change Order #2

23-0075

2/1/2023

$339,444.13

Change Order #3

24-0078

1/10/2024

$759,719.88

Change Order #4

24-0442

6/26/2024

$3,782,603.00

Change Order #5

24-0802

11/20/2024

$279,436.22

Change Order #6

25-

10/1/2025

$4,810,722.37

Total Revised Amount

 

 

$284,999,765.57

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                          $4,810,722.37

 

Prime Vendor:                                           Archer Western/Brown and Caldwell (JV)

Prime Status:                                          Archer Western ($4,329,649.95 or 90.00%) Non-Minority                                                                                                          & Brown and Caldwell ($481,072.22 or 10.00%) Non-                                                                                                         Minority

Location:                                                               Atlanta, GA

County:                                                               Fulton County

Prime Value:                                          $4,810,722.37 or 100.00%

 

Total Contract Value:                     $4,810,722.37 or 100.00%

Total Certified Value:                     $0.00 or 0.00%

 

Exhibits Attached

Exhibit 1: Extension No. 6 to Form of Agreement

Exhibit 2: Performance Evaluation

 

Contact Information (Type Name, Title, Agency and Phone)
title

David Clark, Director, Public Works

 

Contract Attached
title

Yes


Previous Contracts

title

Yes

 

 

Total Contract Value

Original Approved Amount:

$274,768,712.00

Previous Adjustments:

$5,420,331.23

This Request:

$4,810,722.37

TOTAL:

$284,999,765.57


Fiscal Impact / Funding Source

Funding Line 1:

235-540-5400-S157:  W&S Construction-2020, Public Works, Big Creek Expansion

Key Contract Terms

Start Date: Upon BOC Approval

End Date: 10/31/2025

Cost Adjustment: $4,810,722.37

Renewal/Extension Terms


Overall Contractor Performance Rating: 94

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

4/1/2025

7/22/2025