Title: Request approval to renew an existing contract - Department of Public Works, 20ITBC1320A-FB, Rip Rap Crushed Stones in an amount not to exceed $32,590.00 with Luck Stone dba Stephens Industries, LLC. (College Park, GA), to provide rip rap crushed stones. This action exercises the second of two renewal options. No renewal options remain. Effective dates: January 1, 2023, through December 31, 2023. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
Attachments: 1. Exhibit 1: Contract Renewal Agreement, 2. Exhibit 2: Contractor Performance Report, 3. Exhibit 3: Contract Renewal Evaluation Form, 4. 2022-0897
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Department

Public Works

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval to renew an existing contract - Department of Public Works, 20ITBC1320A-FB, Rip Rap Crushed Stones in an amount not to exceed $32,590.00 with Luck Stone dba Stephens Industries, LLC. (College Park, GA), to provide rip rap crushed stones. This action exercises the second of two renewal options. No renewal options remain. Effective dates: January 1, 2023, through December 31, 2023.  (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)     

body


Requirement for Board Action
(Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 02-394(6), the Purchasing Department shall present all renewal requests to the Board of Commissioners at least 90 days prior to the contract renewal date or 60 days if the contract term is six (6) months or less

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Health and Human Services

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background: The Department of Public Works recommends approval to renew existing contract to provide rip rap crushed stone.

 

Scope of Work: The Department request approval to renew existing contract to provide rip rap crushed stones.

 

Community Impact: If timely repairs cannot be made to the water distribution and wastewater collection system, potential impacts to the availability of this infrastructure to our customers can occur.

 

Department Recommendation: Recommend approval.

 

Project Implications: Rip rap crushed stone is necessary for repairs to the wastewater collection system. Failure to approve this contract may delay repairs resulting in discharges of untreated wastewater to the environment.

 

Community Issues/Concerns: No issues were raised by constituents or customers relative to this item.

 

Department Issues/Concerns: The Department has no issues/concerns regarding these contracts.

 

Contract Modification:

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

21-0067

1/20/2021

$32,590.00

1st Renewal

21-0857

11/3/2021

$32.590.00

2nd Renewal

 

 

$32,590.00

Total Revised Amount

 

 

$97,770.00

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                          $32,590.00

 

Prime Vendor:                                          Luck Stone, DBA Stephens Industries, LLC

Prime Status:                                          Non-Minority

Location:                                                               College Park, GA

County:                                                                Fulton County

Prime Value:                                          $32,590.00 or 100.00%

 

Total Contract Value:       $ 32,590.00 or 100.00%
Total M/FBE Value:           $-0-     

 

Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)

Exhibit 1: Contract Renewal Agreement

Exhibit 2: Contractor Performance Report

Exhibit 3: Contract Renewal Evaluation Form

 

Contact Information (Type Name, Title, Agency and Phone)
title

Roy Barnes, Deputy Director, Public Works, 404-612-6317

 

Contract Attached
title

No


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$32,590.00

Previous Adjustments:

$32,590.00

This Request:

$32,590.00

TOTAL:

$97,770.00


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

201-540-5469-1450: Water & Sewer Revenue, Public Works, Maintenance Supplies - $32,590.00

Key Contract Terms

Start Date: 1/1/2023

End Date: 12/31/2023

Cost Adjustment:

Renewal/Extension Terms: No renewal options remain


Overall Contractor Performance Rating: 3.00

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

7/1/2022

9/30/2022