Legislation Details

File #: 26-0760    Version: 1 Name:
Type: CM Action Item - Health and Human Services Status: Agenda Ready
File created: 9/22/2026 In control: Board of Commissioners
On agenda: 11/4/2026 Final action:
Title: Request approval of a Contract Item Agreement (CIA) between Fulton County and the Georgia Department of Transportation (GDOT) for water main relocations associated with the widening and improvements to Abbotts Bridge Road (SR 120) Promise Parkway to Boles Road (Project P.I. No. 721000), in Johns Creek, Georgia, in an estimated amount of $3,206,076.00.
Attachments: 1. Exhibits-A-PI 721000- Fulton - Fulton County W&S - REVISED CIA Agm Pkg 9-8-26
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Department

Public Works

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval of a Contract Item Agreement (CIA) between Fulton County and the Georgia Department of Transportation (GDOT) for water main relocations associated with the widening and improvements to Abbotts Bridge Road (SR 120) Promise Parkway to Boles Road (Project P.I. No. 721000), in Johns Creek, Georgia, in an estimated amount of $3,206,076.00.

body


Requirement for Board Action
(Cite specific Board policy, statute or code requirement)

GA CONST Art. 9, § 3, ¶ I provides that the County may contract for any period not exceeding 50 years with any other public agency, public corporation, or public authority for joint services, for the provision of services, or for the joint or separate use of facilities or equipment; but such contracts must deal with activities, services, or facilities that the contracting parties are authorized by law to undertake or provide. In addition, pursuant to O.C.G.A § 36-10-1, all official contracts entered into by the County governing authority with other persons on behalf of the County shall be in writing and entered on its minutes.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Health and Human Services

 

Commission Districts Affected

All Districts

 

District 1

1

District 2

 

District 3

 

District 4

 

District 5

 

District 6

 


Is this a purchasing item?

No

 

Summary & Background:

 

Scope of Work: The Georgia Department of Transportation (GDOT) is planning improvements to Abbotts Bridge Road (SR 120) between Promise Parkway and Boles Road in Johns Creek. The project will include roadway widening and several intersection upgrades, including turn lanes, landscaped medians, and sidewalk enhancements. As part of this work, approximately 7,225 linear feet of 10‑inch water main and associated appurtenances will need to be relocated within the existing right‑of‑way. Water service to customers will remain uninterrupted throughout the construction period.  GDOT intends to bid the roadway improvements in end‑2026 and has requested execution of a Contract Item Agreement (CIA) with Fulton County to allow GDOT to include the water main relocation work in its bid package. Following award of the construction contract, Fulton County will reimburse GDOT for the water main relocation costs in accordance with the CIA.  Fulton County staff will be on-site during the relocation to ensure all work meets County standards.  The estimated cost for the relocation and installation of the impacted water mains is $3,206,076.00. Funding has been budgeted through the Water and Sewer Fund and is included in the 2016-2026 Capital Improvement Program.

 

Community Impact: Fulton County currently operates 10‑inch and 8‑inch water mains serving properties along Abbotts Bridge Road (SR 120). The planned road improvements will impact these existing water lines, which provide service to developments in the area and support the distribution system supplying the City of Johns Creek.

 

Department Recommendation: The Department of Public Works believes that the most cost‑effective approach to completing the water main relocations is to allow the Georgia Department of Transportation (GDOT) to include the work in its roadway project bid. Therefore, Public Works recommends that Fulton County enter into the Contract Item Agreement (CIA).

 

Project Implications: The road improvements will impact the existing water mains due to grade modifications and roadway widening along Abbotts Bridge Road (SR 120), which require the relocation of water mains and the adjustment of valves to match the proposed roadway surface. These relocations are necessary to maintain uninterrupted water service in the area.

 

Community Issues/Concerns: During construction of the relocations, water service will be maintained, although temporary interruptions may be necessary during tie‑ins to the existing water mains.

 

Department Issues/Concerns: The Public Works Department is not aware of any issues or concerns with this proposed Contract Item Agreement (CIA)

 

Contract Modification:

 

New Procurement

 

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Georgia Department of Transportation (GDOT)

 

Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)

Exhibits-A-PI 721000- Fulton - Fulton County W&S - REVISED CIA Agm Pkg 9-8-26

Contact Information (Type Name, Title, Agency and Phone)
title

Georgia Department of Transportation (GDOT)

 

Contract Attached
title

Yes


Previous Contracts

title

No

 

Total Contract Value

Original Approved Amount:

 

Previous Adjustments:

 

This Request:

$3,206,076.00

TOTAL:

$3,206,076.00


Fiscal Impact / Funding Source

Funding Line 1:

Water & Sewer 203-540-5400-I301