Legislation Details

File #: 26-0591    Version: 1 Name:
Type: CM Action Item - Health and Human Services Status: Agenda Ready
File created: 8/26/2026 In control: Board of Commissioners
On agenda: 9/16/2026 Final action:
Title: Request approval to renew existing contracts - Department of Public Works, 24ITB1335637A-JWT, Sanitary Sewer Easement Maintenance in an amount not to exceed $382,764.50 with Mariani Enterprises, LLC dba Ed Castro Landscape, Inc., (Roswell, GA) to provide easement maintenance in both the North and South Fulton service areas. This action exercises the second of two renewal options. No renewal options remain. Effective dates: January 1, 2027, through December 31, 2027.
Attachments: 1. Exhibit 1: Contract Renewal Agreement, 2. Exhibit 2: Contract Renewal Evaluation Form, 3. Exhibit 3: Contractor Performance Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Department

Public Works

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval to renew existing contracts - Department of Public Works, 24ITB1335637A-JWT, Sanitary Sewer Easement Maintenance in an amount not to exceed $382,764.50 with Mariani Enterprises, LLC dba Ed Castro Landscape, Inc., (Roswell, GA) to provide easement maintenance in both the North and South Fulton service areas. This action exercises the second of two renewal options. No renewal options remain. Effective dates: January 1, 2027, through December 31, 2027.

body


Requirement for Board Action
(Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-394(6), the Purchasing Department shall present all renewal requests to the Board of Commissioners at least 90 days prior to the contract renewal date, 60 days if the contract term is six (6) months or less.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Health and Human Services

 

Commission Districts Affected

All Districts

 

District 1

X

District 2

X

District 3

X

District 4

 

District 5

X

District 6

X


Is this a purchasing item?

Yes

 

Summary & Background: The Department of Public Works requests approval to renew an existing contract with Mariani Enterprises, LLC dba Ed Castro Landscape, Inc. to provide easement maintenance activities in both the North and South Fulton service areas.

 

Scope of Work: This contract includes both sewer and water easement clearing activities in the North Fulton water and wastewater systems and sewer easement clearing activities along the South Fulton wastewater system, on property owned or within easements maintained by Fulton County.

 

Community Impact: Easement clearing activities may impact surrounding neighborhoods because the easement clearing usually results in the removal of trees and shrubs blocking access to the County infrastructure in the easement.

 

Department Recommendation: The Department of Public Works recommends approval.

 

Project Implications: Easement-clearing activities are needed to provide the County with access to conduct maintenance and repairs to the water and wastewater systems.  In the event that access is impeded due to overgrown easements, spills and main breaks could result, which might negatively impact the environment and create potential health concerns.

 

Community Issues/Concerns: Some residents near the easement areas have previously expressed concerns regarding the removal of trees and the existing environment being disturbed.

 

Department Issues/Concerns: No issues/concerns are known with this contract.

 

Contract Modification:

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

25-0077

1/29/2025

$382,764.50

1st Renewal

25-0819

11/5/2025

$382,764.50

2nd Renewal

 

 

$382,764.50

Total Revised Amount

 

 

$1,148,293.50

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                          $382,764.50

 

Prime Vendor:                                          Mariani Enterprises, LLC dba Ed Castro

Prime Status:                     Non-Minority 

Location:                       Roswell, GA

County:                                                               Fulton County

Prime Value:                                          $328,794.71 or 85.90%

 

Subcontractor:                                          CMG Landscape and Maintenance

Subcontractor Status:                     African American Male Business Enterprise

Location:                                                               Roswell, GA

County:                                                               Fulton County

Contract Value:                                          $21,970.68 or 5.74%

 

Subcontractor:                                          Complete Facility

Subcontractor Status:                     African American Female Enterprise

Location:                     Suwanee, GA                                          

County:                                                               Gwinnett County                                                               

Contract Value:                                          $ 21,970.68 or 5.74% 

 

Subcontractor:                                          One Two Tree

Subcontractor Status:                     White Female Business Enterprise

Location:                     Marietta, GA                     

County:                                                               Fayette County

Contract Value:                                          $10,028.43 or 2.62%

Total Contract Value:                     $382,764.50 or 100.00%

Total Certified Value:                     $53,969.79 or 14.10%

 

Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)

Exhibit 1: Contract Renewal Agreement

Exhibit 2: Contract Renewal Evaluation Form

Exhibit 3: Performance Evaluation

 

Contact Information (Type Name, Title, Agency and Phone)
title

Patrick Person, Interim Deputy Director, Public Works 404-612-9429

 

Contract Attached
title

No


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$765,529.00

Previous Adjustments:

$0.00

This Request:

$382,764.50

TOTAL:

$1,148,293.50


Grant Information Summary

Amount Requested:

 

 

Cash

Match Required:

 

 

In-Kind

Start Date:

 

 

Approval to Award

End Date:

 

 

Apply & Accept

Match Account $:

 

 

 

Fiscal Impact / Funding Source

Funding Line 1:

201-540-5459-1160: Water & Sewer Revenue, Public Works, Professional Services - $191,382.25

Funding Line 2:

201-540-5469-1160: Water & Sewer Revenue, Public Works, Professional Services - $191,382.25

Key Contract Terms

Start Date: 1/1/2027

End Date: 12/31/2027

Cost Adjustment:

Renewal/Extension Terms: No renewal options remain


Overall Contractor Performance Rating: 85

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

4/25/2026

7/24/2026