File #: 26-0020    Version: 1 Name:
Type: Consent - Open & Responsible Government Status: Agenda Ready
File created: 1/2/2026 In control: Board of Commissioners
On agenda: 1/21/2026 Final action:
Title: Request approval of a change order less than 10% - Department of Real Estate and Asset Management, 24RFP020124K-JA Design-Build Services for North Fulton HHS Center in the total amount of $706,765.91 with Beck PMI, Joint Venture, comprised of The Beck Group and Peachtree Mechanical Inc. (Atlanta, GA), to modify the existing contract Owner Controlled Contingency to allow the execution of an additional scope of work required for the completion of construction and renovation of North Fulton HHS Center located at 4700 North Point Parkway, Alpharetta, GA 30022. Effective upon BOC approval.
Attachments: 1. Exhibit 1 Change Order No. 1 to Form of Contract- DB HHS Center, 2. Exhibit 2 - Change Order Cost Proposals, 3. Exhibit 3 - Contractor Performance Report - Beck (1)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Department

Real Estate and Asset Management

 

Requested Action

title

 

Request approval of a change order less than 10% - Department of Real Estate and Asset Management, 24RFP020124K-JA Design-Build Services for North Fulton HHS Center in the total amount of $706,765.91 with Beck PMI, Joint Venture, comprised of The Beck Group and Peachtree Mechanical Inc. (Atlanta, GA), to modify the existing contract Owner Controlled Contingency to allow the execution of an additional scope of work  required for the completion of construction and renovation of North Fulton HHS Center located at 4700 North Point Parkway, Alpharetta, GA 30022. Effective upon BOC approval.

body


Requirement for Board Action

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.​

 

Strategic Priority Area related to this item

Open and Responsible Government

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Choose an item.

 

Summary & Background: The approved construction project in progress approved by the BOC as Agenda Item #24-0797 on November 24, 2024, responds to the need to expand delivery of Health and Human Services at the property located at 4700 North Point Pkwy.  This construction project will allow for services currently being offered in either leased facilities or facilities that have exceeded their useful life expectancy to be relocated to a modern, County-owned facility.

 

The existing facility is a two-story 108,000 (+/-) sq. ft. building on North Point Parkway, a former data center. Based on preliminary test fits, the services included at this location will be the Department of Health (State - Administration, nursing, environmental, dentistry, traveling nursing programs, vital records, and W.I.C) Behavioral Health - Youth, Adult, and Developmental Disabilities, Department of Real Estate and Asset Management (DREAM), Emergency Management Agency, Superior Court DUI Services, Senior Services Programming with future inclusion of wrap around support services. 

 

The total project costs approved of $15,417,450.00 included an original Owner Controlled Contingency amount of $1,069,441.00. To date, approved scope of work Credits and VE options accepted have yielded a credit of $393,751.00 for a total available Owner Controlled contingency of $1,463,192.00 (see details below).  The Owner has approved changes to the scope of work that have exhausted the available Owner Controlled contingency.  Additional changes to the scope of work identified exceed the available contingency amount, thus requiring this request for additional project funding to complete this construction project.

 

Original Contractual Owner Controlled Contingency

     1,069,441.00

 

 

CREDITS

 

PCO #001 - VE Options Target

 $        48,324.00

PCO #018 - Buyout Savings - Flooring

 $        59,780.00

PCO #018 - Buyout Savings -Doors Frames Hardware Material

 $     114,897.00

PCO #018 - Buyout Savings - Millwork

 $     130,867.00

PCO #018 - Buyout Savings - Spray Applied Fireproofing

 $        39,883.00

 

 

Subtotal Credits

 $     393,751.00

TOTAL Available Owner Controlled Contingency:

 $ 1,463,192.00

 SCOPE COVERED BY CONTRACTUAL CONTINGENCY   Furniture Fixtures and Equipment  $     658,369.00   Access Control  / Network Equipment / WAP's / CCTV  $     486,880.00   Audio Visual  $     370,943.99   Misc - Appliances, Automated External Defibrillators, etc  $        49,229.92   Moving Services  $        15,990.00   Estimate - Additional Moving Services, Coax Cable and Duress Buttons  $        45,000.00                  Owner Controlled Contingency Required for Listed Items   $ 1,626,412.91  

 

                 TOTAL Available Owner Controlled Contingency                            $1,463,192.00

 

            Owner Controlled Contingency Shortfall Included Below         ($163,220.91)

 

Scope of Work: The initial project consists of the design and renovation of the facility’s interior encompassing approximately 65% of the facility square footage. Additional modifications to the existing contract scope of work will allow the execution required for the completion of construction and renovation of North Fulton HHS Center located at 4700 North Point Parkway, Alpharetta, GA 30022.

 

Additional Owner Controlled Contingency Requested for Scope of Work Listed:

$706,765.91

  

 

Shortfall Owner Controlled Contingency Needed

$163,220.91

Furniture Fixtures & Equipment

 

Additional Moving Services

 

Coax Cable

 

Duress Buttons

 

W&A Testing/Investigation

 $            9,718.00

Wet Seal & Elastomeric Coating

 $       355,921.00

RAF Repair (DREAM Shop)

 $            3,864.00

Commissioner Thorne Offices

 $          30,838.00

Oral Health  Mechanical, Electrical and Plumbing Additions

 $          67,160.00

Walk Off Mat Concrete Repair

 $            1,769.00

Monument sign refurbishment

 $            9,900.00

Digital Displays (1st, 2nd floor)

 $          14,282.00

Hose Bibbs added to roof

 $          15,533.00

Exterior Signage

 $          10,000.00

Interior Signage

 $          24,560.00

Additional Finishes

 $           9,718.00

 

The additional audio visual equipment scope of work includes furnishing and installing all projectors, screens, speakers, cameras, and presentation equipment per the approved drawings and specifications. Includes general conditions to coordinate delivery and installation of AV scope beyond the January 15, 2026 contractual completion date.

 

This change order will impact the original project schedule which called for achieving substantial completion with a temporary certificate of occupancy (TCO) within 270 calendar days of notice to proceed and final completion in 300 calendar days or as agreed between the County and the Design/Builder.

 

Community Impact: The successful completion of this new location for several Health and Human Services initiatives ensures that citizens of North Fulton and surrounding areas can access these critical services to meet their needs.

 

Department Recommendation: The Department of Real Estate and Asset Management recommends approval of Change No. 1.

 

The BOC approved, via Agenda Item #24-0797 on November 20, 2024, the recommended proposal in the amount of $15,417,450.00 with Beck PMI, Joint Venture, comprised of The Beck Group and Peachtree Mechanical Inc. (Atlanta, GA), to provide Design/Build services for the construction and renovation of 4700 North Point Parkway, Alpharetta, GA 30022.

 

Now, Department of Real Estate and Asset Management recommends approval to move forward with Change Order No. 1 in the total amount of $706,765.91, for additional funding to allow the Beck PMI, JV to continue providing, without disruption, construction of the North Fulton HHS Center located at 4700 North Point Parkway, Alpharetta, GA 30022.

 

The recommended Construction Manager will work in collaboration with the Department of Real Estate and Asset Management, Project Management Team.

 

Project Implications: This contract’s intent is to complete the construction/renovation design project of this new Health and Human Services Center for North Fulton that will allow Fulton County staff to provide a one-stop location for several Health and Human Services initiatives to ensure that citizens of North Fulton and surrounding areas can access these critical services to meet their needs.

 

Community Issues/Concerns: None that the Department is aware of.

Department Issues/Concerns: If this proposal is not approved, the County does not have the capacity, or the expertise, to perform the Design/Build services for the construction and renovation to the new Fulton County Health and Human Services Center for North Fulton.

 

Contract Modification

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

24-0797

11/20/2024

$15,417,450.00

Change Order No. 1

 

 

$706,765.91

Total Revised Amount

 

 

$16,124,215.91

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                   $706,765.91

Prime Vendor:                                      The Beck Group / Peachtree Mechanical

                                                                                    Inc., (JV)

Prime Status:                                        The Beck Group - Non-Minority ($565,412.72 or 80.00%) and Peachtree Mechanical Inc. - White Female American

Business Enterprise ($141,353,18 or 20.00%)

Location:                                              Atlanta, GA

County:                              Fulton County

 

Total Contract Value:                            $706,765.91 or 100.00%

Total Certified Value:                            $141,353,18 or 20.00%

 

Exhibits Attached

Exhibit 1: Change Order No. 1 to Form of Contract

Exhibit 2: Change Order Cost Proposals

Exhibit 3: Performance Evaluation

 

Contact Information
title

Joseph N. Davis, Director, Department of Real Estate and Asset Management, (404) 612-3772

 

Contract Attached
title

Yes


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$15,417,450.00

Previous Adjustments:

$0.00

This Request:

$706,765.91

TOTAL:

$16,124,215.91


Fiscal Impact / Funding Source

Funding Line 1:

540-520-5200-1424: Capital, Real Estate and Asset Management, Renovations - $706,765.91

Key Contract Terms

Start Date: Upon BOC Approval

End Date: Final completion 300 days or as agreed between the County and the Design/Builder

Cost Adjustment: $706,765.91

Renewal/Extension Terms   N/A


Overall Contractor Performance Rating: 82

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

10/8/2025

1/7/26