File #: 25-0643    Version: 1 Name:
Type: CM Action Item - Health and Human Services Status: Passed
File created: 6/3/2025 In control: Board of Commissioners
On agenda: 9/3/2025 Final action: 9/3/2025
Title: Request approval to increase spending authority - Public Works, 22ITB136990K-JA Standby Miscellaneous Construction, Water System Services in an amount not to exceed $848,021.76 with Site Engineering, Inc (Atlanta, GA), to provide miscellaneous construction services for the Fulton County water distribution network. Effective upon BOC approval. (APPROVED)
Attachments: 1. Change Order No. 1 to Form of Contract, 2. Contractor Performance Report - Site Engineering

Department

Public Works

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval to increase spending authority - Public Works, 22ITB136990K-JA Standby Miscellaneous Construction, Water System Services in an amount not to exceed $848,021.76 with Site Engineering, Inc (Atlanta, GA), to provide miscellaneous construction services for the Fulton County water distribution network. Effective upon BOC approval.  (APPROVED)

body

 

Requirement for Board Action (Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Health and Human Services

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background: This contract was initially approved by the BOC for one year with 2 one-year renewal options. The contract is currently in year #3 which is the final year. The Public Works Department seeks to have unused funding from Years 1 and 2 allocated to this final year. The Year 1 Purchase Order (PO 540 22ITB136990K-JA) has an unallocated balance of $518,301.57, while the Year 2 Purchase Order (PO 540 22ITB136990K-JA-R1) has an unallocated balance of $329,720.19. In total, the department aims to utilize the unused total of $848,021.76 from the first two years within Year 3 of this contract.

 

Scope of Work: The scope of work under this BOC Item will remain unchanged as approved by the Fulton County BOC under Item #23-0206 and all subsequent actions. This contract provides for on-call, standby, and emergency construction services dealing with the repair and installation of water mains, water service lines, and other miscellaneous water service-related facilities located in the North Fulton water service area. The contractor provides the necessary crew and equipment as directed by Public Works staff on an as needed basis. 

 

Community Impact: The work under this contract ensures the North Fulton water distribution system continues to be maintained in the most efficient manner. This system in responsible for providing the residents and businesses potable water.

 

Department Recommendation: The Public Works Department recommends approval of this item.

 

Project Implications: Approval of this item will ensure the availability of supplemental manpower and equipment through on-call services to address emergencies and support repair and replacement needs within the water distribution system. Additionally, approval will enable the Department to maximize the use of allocated funding to complete pending projects.

 

Community Issues/Concerns: No community issues or concerns have been noted by the Public Works Department.

 

Department Issues/Concerns: Without approval of this item the Public Works Department will not be able to utilize unallocated balances that remain on the year 1 and year 2 purchase orders.

 

Contract Modification

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

23-0206

3/15/2023

$1,200,000.00

1st Renewal

24-0203

3/20/2024

$1,200,000.00

2nd Renewal

24-0892

12/18/2024

$1,200,000.00

Increase Spending Authority

 

 

$848,021.76

Total Revised Amount

 

 

$3,600,000.00

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                           $848,021.76

 

Prime Vendor:                                          Site Engineering, Inc.  

Prime Status:                                          Small Business Enterprise

Location:                                                               Atlanta, GA

County:                                                               Fulton County

Prime Value:                                          $720,181.50 or 85.00%

 

Subcontractor:                                           JDJ 

Subcontractor Status:                     African American Male Business Enterprise

Location:                                                               Decatur, GA

County:                                                               DeKalb County

Contract Value:                                          $127,203.26 or 15.00%

 

Total Contract Value:                     $848,021.76 or 100.00%

Total Certified Value:                      $848,021.76 or 100.00%

 

Exhibits Attached

Exhibit 1: Change Order No. 1 to Form of Agreement

Exhibit 2:  Performance Evaluation

Contact Information (Type Name, Title, Agency and Phone)
title

David E. Clark, Director, Public Works 404-612-2804

 

Contract Attached
title

Yes


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$1,200,000.00

Previous Adjustments:

$2,400,000.00

This Request:

$848,021.76

TOTAL:

$3,600,000.00


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

203-540-5400-H065: Water & Sewer R&E, Public Works, Misc Water Line Proj

Key Contract Terms

Start Date:

 

End Date:

 

Cost Adjustment:

 

Renewal/Extension Terms:

 


Overall Contractor Performance Rating: 100

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

2/9/2025

5/8/2025