File #: 22-0759    Version: 1 Name:
Type: Consent - Open & Responsible Government Status: Agenda Ready
File created: 9/21/2022 In control: Board of Commissioners
On agenda: 10/19/2022 Final action:
Title: Request approval of a change order less than 10% - Department of Real Estate and Asset Management, 21RFP132087K-DB, Design/Build Services for the Fulton County Government Center Cooling Tower Repair and Retrofit in the amount of $78,562.00 with Mallory & Evans Service Co., Inc. (Scottdale, GA), to modify the existing scope of work to provide additional repairs and replacement of two (2) Fan Assemblies and 29 Fissure Cracks in the concrete wall of the water tank located in the Government Center Complex and to extend the existing contract term for an additional four (4) month period to complete the work through December 31, 2022. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
Attachments: 1. Exhibit 1 Change Order No. 1 to Form of Contract, 2. Exhibit 2 Change Order Cost Proposal Memo, 3. Exhibit 3 Contractor's Performance Report, 4. 2022-0759
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Department

Real Estate and Asset Management

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval of a change order less than 10% - Department of Real Estate and Asset Management, 21RFP132087K-DB, Design/Build Services for the Fulton County Government Center Cooling Tower Repair and Retrofit in the amount of $78,562.00 with Mallory & Evans Service Co., Inc. (Scottdale, GA), to modify the existing scope of work to provide additional repairs and replacement of two (2) Fan Assemblies and 29 Fissure Cracks in the concrete wall of the water tank located in the Government Center Complex and to extend the existing contract term for an additional four (4) month period to complete the work through December 31, 2022.  Effective upon BOC approval.  (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)  

body

Requirement for Board Action (Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Open and Responsible Government

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background Request approval of a change order of less than 10% to modify the existing Scope of Work, to provide additional repairs and replacement of two (2) Fan Assemblies and 29 Fissure Cracks in the concrete wall of the water tank located in the Fulton County Government Center Complex. 

 

Scope of Work: Request approval of Change Order No. 1 to provide additional repairs and replacement of two (2) Fan Assemblies and 29 Fissure Cracks in the concrete wall of the water tank located in the Fulton County Government Center Complex.

 

The two (2) Fan Assemblies are comprised of fans, motors, gearboxes, and couplings that were designed for 100,000 hours of operation if properly maintained but may be original to the building. Specific deficiencies include corroded fans having lost their protective exterior coating, gearboxes leaking oil and showing interior corrosion, failed or ill fitted omega couplings/ bushings, and non-functioning vibration and oil level switches. These conditions suggest a full replacement of all components of the Fan Assemblies are needed, rather than repair of the non-functioning ones.

 

Additionally, the investigation identified 29 fissure cracks in the concrete wall of the water tank requiring repair, more than the twelve (12) programmed in the Project scope. None of the cracks are structural in nature but without repair could lead to water leaks and wall deterioration. Repairing all 29 fissure cracks helps ensure the longevity of the Cooling Tower's structural integrity.

 

Fan Assemblies and additional Fissure Cracks Costs to Repair/Replace:

 

Parts

Condition

Completion

Costs

Motors

Damaged and corroded

4th Qtr. 2022

$4,738.86

Gearboxes

Leaking oil. Interior corrosion. Damaged impeller and shaft from bearing failure.

4th Qtr. 2022

$9,797.90

Omega Couplings/Bushing

Deteriorated and ill-filling.

4th Qtr. 2022

$2,538.21

Vibration & oil Level Switches

Worn and non-functioning

4th Qtr. 2022

$2,298.53

Fans

Heavily corroded. Protective coating deteriorated.

4th Qtr. 2022

$20,747.38

Labor, Freight & Taxes

N/A

4th Qtr. 2022

$12,501.12

Markup

N/A

N/A

$6,223.00

Fan Assemblies Subtotal

N/A

4th Qtr. 2022

$58,845.00

Fissure Cracks Repairs Subtotal

Additional seventeen (17) Fissure Crack Repairs above the twelve (12) in Scope.

4th Qtr. 2022

$12,575.00

Contingency (10%)

$7,142.00

Total Costs

$78,562.00

 

This work to be performed under this Change Order is necessary and coupled with rising construction pricing, scarcity of replacement parts, and scheduling impacts, we believe this Change Request #1 is merited.

 

Community Impact: Maintaining Cooling Tower systems in a reliable working condition ensures proper air quality and temperature in all buildings visited by the public.

 

Department Recommendation: The Department of Real Estate and Asset Management recommends approval.

 

The BOC approved on February16, 2022, Item #22-0125, the recommended proposal #21RFP132087K-DB, with Mallory & Evans Service, Inc. in the amount of $1,677,706, to provide complete design and construction services for the retrofit of the counter flow ceramic cooling tower serving the chiller plant and emergency generators at the Fulton County Government Center Complex.

 

Change Order No. 1 will allow the repair/replacement of two (2) Fan Assemblies and all 29 Fissure Cracks helps ensure the longevity of the Cooling Tower's structural integrity and extend the existing contract term for an additional four (4) months period to complete the work through December 31, 2022. This extension is solely attributable to the availability and delivery of necessary replacements parts which can be up to 16 weeks in today’s marketplace. 

 

The HVAC Contractor (Mallory & Evans) will work in collaboration with the Department of Real Estate and Asset Management, Project Management Team.

 

Project Implications: This effort and impact are necessary to allow the completion of additional repairs and replacement of two (2) Fan Assemblies and 29 Fissure Cracks in the concrete wall of the water tank located in the Fulton County Government Center Complex.

 

Community Issues/Concerns: None of which the Department is aware.

 

Department Issues/Concerns: If this Change Order is not approved, there may be a potential disruption of the additional repairs and replacement of two (2) Fan Assemblies and 29 Fissure Cracks in the concrete wall of the water tank located in the Fulton County Government Center Complex.

 

Contract Modification

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

22-0125

2/16/22

$1,677,706.00

Change Order No. 1

 

 

$78,562.00

Total Revised Amount

 

 

$1,756,268.00

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                          $78,562.00 

Prime Vendor:                     Mallory & Evans Service Co.

Prime Status:                     Non-Minority

Location:                                                               Scottdale, GA

County:                                                               Dekalb County

Prime Value:                                          $78,562.00 or 46.00%

 

Total Contract Value:                      $78,562.00 or 100.00%

Total M/FBE Value:                      $-0-

 

Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)

Exhibit 1: Change Order No. 1 to Form of Contract

Exhibit 2: Change Order Cost Proposal Memo

Exhibit 3: Contractor’s Performance Report

 

Contact Information (Type Name, Title, Agency and Phone)
title

Joseph N. Davis, Director, Department of Real Estate and Asset Management, (404) 612-3772

 

Contract Attached
title

Yes


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$1,677,706.00

Previous Adjustments:

$0.00

This Request:

$78,562.00

TOTAL:

$1,756,268.00


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

532-520-5200-K008: FCURA, Real Estate and Asset Management, MEP Improvements-FCURA - $78,562.00

 

Key Contract Terms

Start Date: Upon BOC Approval

End Date: 12/31/2022

Cost Adjustment

Renewal/Extension Terms: 4 months extension


Overall Contractor Performance Rating: 4.00

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

3/8/2022

8/31/2022