Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title
Request approval of a change order less than 10% - Department of Real Estate and Asset Management, 21RFP132087K-DB, Design/Build Services for the Fulton County Government Center Cooling Tower Repair and Retrofit in the amount of $78,562.00 with Mallory & Evans Service Co., Inc. (Scottdale, GA), to modify the existing scope of work to provide additional repairs and replacement of two (2) Fan Assemblies and 29 Fissure Cracks in the concrete wall of the water tank located in the Government Center Complex and to extend the existing contract term for an additional four (4) month period to complete the work through December 31, 2022. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
body
Requirement for Board Action (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.
Strategic Priority Area related to this item (If yes, note strategic priority area below)
Open and Responsible Government
Commission Districts Affected
All Districts ☒
District 1 ☐
District 2 ☐
District 3 ☐
District 4 ☐
District 5 ☐
District 6 ☐
Is this a purchasing item?
Yes
Summary & Background Request approval of a change order of less than 10% to modify the existing Scope of Work, to provide additional repairs and replacement of two (2) Fan Assemblies and 29 Fissure Cracks in the concrete wall of the water tank located in the Fulton County Government Center Complex.
Scope of Work: Request approval of Change Order No. 1 to provide additional repairs and replacement of two (2) Fan Assemblies and 29 Fissure Cracks in the concrete wall of the water tank located in the Fulton County Government Center Complex.
The two (2) Fan Assemblies are comprised of fans, motors, gearboxes, and couplings that were designed for 100,000 hours of operation if properly maintained but may be original to the building. Specific deficiencies include corroded fans having lost their protective exterior coating, gearboxes leaking oil and showing interior corrosion, failed or ill fitted omega couplings/ bushings, and non-functioning vibration and oil level switches. These conditions suggest a full replacement of all components of the Fan Assemblies are needed, rather than repair of the non-functioning ones.
Additionally, the investigation identified 29 fissure cracks in the concrete wall of the water tank requiring repair, more than the twelve (12) programmed in the Project scope. None of the cracks are structural in nature but without repair could lead to water leaks and wall deterioration. Repairing all 29 fissure cracks helps ensure the longevity of the Cooling Tower's structural integrity.
Fan Assemblies and additional Fissure Cracks Costs to Repair/Replace:
Parts |
Condition |
Completion |
Costs |
Motors |
Damaged and corroded |
4th Qtr. 2022 |
$4,738.86 |
Gearboxes |
Leaking oil. Interior corrosion. Damaged impeller and shaft from bearing failure. |
4th Qtr. 2022 |
$9,797.90 |
Omega Couplings/Bushing |
Deteriorated and ill-filling. |
4th Qtr. 2022 |
$2,538.21 |
Vibration & oil Level Switches |
Worn and non-functioning |
4th Qtr. 2022 |
$2,298.53 |
Fans |
Heavily corroded. Protective coating deteriorated. |
4th Qtr. 2022 |
$20,747.38 |
Labor, Freight & Taxes |
N/A |
4th Qtr. 2022 |
$12,501.12 |
Markup |
N/A |
N/A |
$6,223.00 |
Fan Assemblies Subtotal |
N/A |
4th Qtr. 2022 |
$58,845.00 |
Fissure Cracks Repairs Subtotal |
Additional seventeen (17) Fissure Crack Repairs above the twelve (12) in Scope. |
4th Qtr. 2022 |
$12,575.00 |
Contingency (10%) |
$7,142.00 |
Total Costs |
$78,562.00 |
This work to be performed under this Change Order is necessary and coupled with rising construction pricing, scarcity of replacement parts, and scheduling impacts, we believe this Change Request #1 is merited.
Community Impact: Maintaining Cooling Tower systems in a reliable working condition ensures proper air quality and temperature in all buildings visited by the public.
Department Recommendation: The Department of Real Estate and Asset Management recommends approval.
The BOC approved on February16, 2022, Item #22-0125, the recommended proposal #21RFP132087K-DB, with Mallory & Evans Service, Inc. in the amount of $1,677,706, to provide complete design and construction services for the retrofit of the counter flow ceramic cooling tower serving the chiller plant and emergency generators at the Fulton County Government Center Complex.
Change Order No. 1 will allow the repair/replacement of two (2) Fan Assemblies and all 29 Fissure Cracks helps ensure the longevity of the Cooling Tower's structural integrity and extend the existing contract term for an additional four (4) months period to complete the work through December 31, 2022. This extension is solely attributable to the availability and delivery of necessary replacements parts which can be up to 16 weeks in today’s marketplace.
The HVAC Contractor (Mallory & Evans) will work in collaboration with the Department of Real Estate and Asset Management, Project Management Team.
Project Implications: This effort and impact are necessary to allow the completion of additional repairs and replacement of two (2) Fan Assemblies and 29 Fissure Cracks in the concrete wall of the water tank located in the Fulton County Government Center Complex.
Community Issues/Concerns: None of which the Department is aware.
Department Issues/Concerns: If this Change Order is not approved, there may be a potential disruption of the additional repairs and replacement of two (2) Fan Assemblies and 29 Fissure Cracks in the concrete wall of the water tank located in the Fulton County Government Center Complex.
Contract Modification
Current Contract History |
BOC Item |
Date |
Dollar Amount |
Original Award Amount |
22-0125 |
2/16/22 |
$1,677,706.00 |
Change Order No. 1 |
|
|
$78,562.00 |
Total Revised Amount |
|
|
$1,756,268.00 |
Contract & Compliance Information (Provide Contractor and Subcontractor details.)
Contract Value: $78,562.00
Prime Vendor: Mallory & Evans Service Co.
Prime Status: Non-Minority
Location: Scottdale, GA
County: Dekalb County
Prime Value: $78,562.00 or 46.00%
Total Contract Value: $78,562.00 or 100.00%
Total M/FBE Value: $-0-
Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)
Exhibit 1: Change Order No. 1 to Form of Contract
Exhibit 2: Change Order Cost Proposal Memo
Exhibit 3: Contractor’s Performance Report
Contact Information (Type Name, Title, Agency and Phone)
title
Joseph N. Davis, Director, Department of Real Estate and Asset Management, (404) 612-3772
Contract Attached
title
Yes
Previous Contracts
title
Yes
Total Contract Value
Original Approved Amount: |
$1,677,706.00 |
Previous Adjustments: |
$0.00 |
This Request: |
$78,562.00 |
TOTAL: |
$1,756,268.00 |
Grant Information Summary
Amount Requested: |
|
☐ |
Cash |
Match Required: |
|
☐ |
In-Kind |
Start Date: |
|
☐ |
Approval to Award |
End Date: |
|
☐ |
Apply & Accept |
Match Account $: |
|
|
|
Fiscal Impact / Funding Source
Funding Line 1:
532-520-5200-K008: FCURA, Real Estate and Asset Management, MEP Improvements-FCURA - $78,562.00
Key Contract Terms |
Start Date: Upon BOC Approval |
End Date: 12/31/2022 |
Cost Adjustment: |
Renewal/Extension Terms: 4 months extension |
Overall Contractor Performance Rating: 4.00
Would you select/recommend this vendor again?
Yes
Report Period Start: |
Report Period End: |
3/8/2022 |
8/31/2022 |