Title: Request approval of an Indemnification, Maintenance, and Land Use Agreement for Private Improvement (Indemnification Agreement) between Fulton County, a political subdivision of the State of Georgia, and Milton Land Invest, Inc. for the purpose of granting conditional approval to allow flat work and landscaping within the County's existing water line easement area at 1240 Mayfield Road, Milton, Georgia 30009. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
Attachments: 1. Heatherton WL IA executed, 2. 2024-0031
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Department

Real Estate and Asset Management

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

Request approval of an Indemnification, Maintenance, and Land Use Agreement for Private Improvement (Indemnification Agreement) between Fulton County, a political subdivision of the State of Georgia, and Milton Land Invest, Inc. for the purpose of granting conditional approval to allow flat work and landscaping within the County’s existing water line easement area at 1240 Mayfield Road, Milton, Georgia 30009. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)   

body

 

Requirement for Board Action (Cite specific Board policy, statute or code requirement)

Fulton County is authorized to grant an encroachment on its water line/vault easement pursuant to Fulton County Code, Subpart B-Code of Resolutions - Appendix A - Subdivision Regulations, Article IX (Required Improvements), Section 9.5.5(c), which states the following in part:  “No retaining wall, building, pole, sign or other vertical structure shall be constructed in sanitary and storm sewer easements, including vehicular access easements around structures, without approval from the [Director of Public Works].”

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Regional Leadership

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     

 

Is this a purchasing item?

No

 

Summary & Background (First sentence includes Agency recommendation. Provide an executive summary of the action that gives an overview of the relevant details for the item.)

 

Scope of Work: Milton Land Invest, Inc., the owner of the real property located at 1240 Mayfield Road, Milton, Georgia 30009 is requesting the conditional approval of the Fulton County Board of Commissioners to allow flat work and landscaping within the County’s existing water line easement.

At the request of the fee simple property owner, Milton Land Invest, Inc., the Fulton County Department of Real Estate and Asset Management and the Fulton County Department of Public Works request approval to amend the terms of the County’s water line easement for this location.   

 

The Department of Public works has completed an onsite assessment of the encroachment area of approximately 5,381 square feet and confirmed the County’s water system will not be adversely impacted and can continue to be properly maintained if this encroachment is granted.

 

The purpose of the Indemnification Agreement is to affirm the terms of Fulton County’s conditional approval of the encroachment of private improvements within the County’ water line easement area at 1240 Mayfield Road, Milton, Georgia 30009

 

Community Impact: The Indemnification Agreement allows Fulton County full access to maintain its water line while granting the property owner conditional approval to install and maintain flatwork and landscaping within the County’s water line easement area.

 

Department Recommendation: The Department of Real Estate and Asset Management accepts the conclusion of the Department of Public Works to accept the terms of the Indemnification Agreement and recommends its approval.

 

Project Implications: No negative impacts to water service or access to the water line for maintenance will result by allowing flatwork and landscaping on the property within the vicinity of the water line. 

 

Community Issues/Concerns: None.

 

Department Issues/Concerns: None.

 