Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title
Request approval of a change order less than 10% - Department of Public Works, 20ITBC124903A-FB, Corporation Stops and Brass Fittings to increase the unit prices as outlined in the attached pricing sheet with Delta Municipal Supply Company (Lawrenceville, GA), to provide corporation stops and brass fittings. No additional funding is required. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
body
Requirement for Board Action (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.
Strategic Priority Area related to this item (If yes, note strategic priority area below)
Health and Human Services
Commission Districts Affected
All Districts ☐
District 1 ☒
District 2 ☒
District 3 ☐
District 4 ☐
District 5 ☐
District 6 ☐
Is this a purchasing item?
Yes
Summary & Background: Department of Public Works recommends approval of change order less than 10%, 20ITBC124903A-FB, Corporation Stops and Brass Fittings to increase the unit prices as outlined in the attached pricing sheet.
Scope of Work: The contract with Delta Municipal Supply Company provides for the procurement of corporation stops and brass fittings for water service installation, repair and maintenance for the North Fulton water distribution system. The renewal of the 2022 contract was approved by the Board of Commissioners on October 20, 2021. However, due to the pandemic, which is impacting the supply chain, Delta Municipal Supply Company requests an average increase of 28% of the previously approved unit prices. The new unit prices for the various materials purchased by Public Works under this contract are shown in Exhibit 1. If this contract with the revised unit prices is approved, the contract amount will remain at $200,000.00 and will not be increased without BOC approval.
Community Impact: Approval of unit price increases will avoid delays in procurement of corporation stops and brass fittings. Failure to procure and maintain these items in stock can negatively impact the operation of the Water Services Division in maintaining water systems and services.
Department Recommendation: The Department of Public Works recommends approval of change order less than 10% to the contract with Delta Municipal Supply Company not to exceed the awarded amount of $200,000.00.
Project Implications: Increase in unit cost without increasing the awarded contract amount may inhibit the ability to procure corporation stops and brass fittings for water service installation, repair and maintenance for the North Fulton water distribution system.
Community Issues/Concerns: Public Works staff is not aware of any community issues or concerns.
Department Issues/Concerns: The Department of Public Works does not have any issues or concerns with the proposed price increase.
Contract Modification:
|
Current Contract History |
BOC Item |
Date |
Dollar Amount |
|
Original Award Amount |
20-0404 |
6/3/2020 |
$266,236.72 |
|
1st Renewal |
20-0960 |
12/16/2020 |
$266,236.72 |
|
2nd Renewal |
21-0821 |
10/20/2021 |
$200,000.00 |
|
Change Order No. 1 |
|
|
$0.00 |
|
Total Revised Amount |
|
|
$732,473.44 |
Contract & Compliance Information (Provide Contractor and Subcontractor details.)
Contract Value: $No Cost
Prime Vendor: Delta Municipal Supply Co.
Prime Status: Non-Minority
Location: Lawrenceville, GA
County: Gwinnett County
Prime Value: $No Cost
Subcontractor: None
Total Contract Value: $No Cost
Total M/FBE Value: $0
Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)
Exhibit 1: Change Order Agreement No.1
Exhibit 2: Contractor Performance Report
Exhibit 3: Revised Pricing Sheet
Contact Information (Type Name, Title, Agency and Phone)
title
Nick Ammons, Public Works, Deputy Director - 404-612-7530
Contract Attached
title
No
Previous Contracts
title
Yes
Total Contract Value
|
Original Approved Amount: |
$266,236.72 |
|
Previous Adjustments: |
$466,236.72 |
|
This Request: |
$0.00 |
|
TOTAL: |
$732,473.44 |
Grant Information Summary
|
Amount Requested: |
|
☐ |
Cash |
|
Match Required: |
|
☐ |
In-Kind |
|
Start Date: |
|
☐ |
Approval to Award |
|
End Date: |
|
☐ |
Apply & Accept |
|
Match Account $: |
|
|
|
Fiscal Impact / Funding Source
Funding Line 1:
203-540-5453-1450: Water & Sewer R & E, Public Works, Maintenance Supplies - $0.00
|
Key Contract Terms |
|
Start Date: Upon approval |
End Date: 12/31/2022 |
|
Cost Adjustment: |
Renewal/Extension Terms: |
Overall Contractor Performance Rating: 4.0
Would you select/recommend this vendor again?
Yes
|
Report Period Start: |
Report Period End: |
|
1/1/2021 |
7/31/2021 |