File #: 22-0924    Version: 1 Name:
Type: CM Action Item - Open & Responsible Government Status: Passed
File created: 10/4/2022 In control: Board of Commissioners
On agenda: 12/7/2022 Final action: 12/7/2022
Title: Request approval to renew an existing contract - Fulton County Information Technology (FCIT), 20ITB042220B-FB, Countywide Structured Cabling and Physical Security in the amount not to exceed $5,673,800.00 with GC&E Systems Group, Inc. (Norcross, GA) to provide countywide structured cabling services. This action exercises the third of three renewal options. No renewal options remain. Effective dates: January 1, 2023 through December 31, 2023. (APPROVED)
Attachments: 1. Exhibit 1 GCE Contractor's Performance Report, 2. Exhibit 2 Contract Renewal Evaluation, 3. Exhibit 3 Renewal Contract Agreement No.pdf, 4. Exhibit 4 Proposed Projects - GCE FY23, 5. 2022-0924

 

Department

Information Technology

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval to renew an existing contract - Fulton County Information Technology (FCIT), 20ITB042220B-FB, Countywide Structured Cabling and Physical Security in the amount not to exceed $5,673,800.00 with GC&E Systems Group, Inc. (Norcross, GA) to provide countywide structured cabling services. This action exercises the third of three renewal options. No renewal options remain.  Effective dates: January 1, 2023 through December 31, 2023.  (APPROVED)  

 

body

Requirement for Board Action (Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-394(6), the Purchasing Department shall present all renewal requests to the Board of Commissioners at least 90 days prior to the contract renewal date, 60 days if the contract term is six (6) months or less.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Open and Responsible Government

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background

This request of ($5,673,800.00) represents a 62% ($2,153,830.00) increase in spending authority FY2023 over FY2022 due to significant physical security and network infrastructure initiatives countywide.  Requesting authority for replacement of critical end-of-life infrastructure equipment associated with enterprise systems (Access Control System, Video Surveillance and supporting structured cabling requirements impacting key county facilities (Justice Center, Juvenile Court, Government Center, Libraries, and Remote facilities)).   All departments countywide will be impacted by these initiatives.

Key Projects to be addressed:

                     Physical Security Upgrades - Replacement of End of Life/End of Service Cisco Hardware supporting significant access control system components - Initiate in Q1

                     Elections Shared Warehouse Spaces -  Phase II - Impacting (8) Departments - Q1

                     Juvenile Court Physical Security projects - Major Access Control System upgrade enhancements Q1

                     Senior Services Centers -  Cabling and Physical Security requirements 14 locations - proposed Q1-Q2

                     Government Center Pandemic Proofing - This will include the renovation of the Government Center Complex to optimize office space.  Project will renovate all office areas of the facility. Projecting construction to begin by Q3.

                     Animal Shelter - New Construction - IT Infrastructure Requirements (Q1-Q3)

                     Public Works Water Treatment Facilities - Physical Security Installation and upgrades - Water Towers, Substations, Reclamation and pump Stations  owned by Fulton County to begin by Q1-Q2

 

Scope of Work: Countywide structured cabling services will consist of installing and maintaining Main Distribution Frames (MDFs), Intermediate Distribution Frames (IDFs), voice/data cabling comprised of copper and fiber to all County building locations. This contract renewal will ensure that materials, equipment, and services required for cabling for the transformational consolidated warehouse, public safety and justice facilities, animal shelter, library renovations, network refresh to support wireless devices, physical security of county facilities, etc. 

 

Community Impact: The approval of this item will allow community projects such as the transformational consolidated warehouse, public safety and justice facilities, animal shelter, library renovations, etc.

 

Department Recommendation:  Department recommends approval to renew contract.

 

Project Implications: The County’s facilities and infrastructure improvement plan/projects will be disrupted without a valid cabling contract.

 

Community Issues/Concerns: There are no community issues/concerns.

 

Department Issues/Concerns: The Countywide cabling contract is essential to FCIT to ensure consistency, standardization, and quality of cabling throughout facilities all over the County.

 

Contract Modification

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

20-0431

06/17/20

$1,615,000.00

1st Renewal

20-0847

11/18/20

$2,319,000.00

2nd Renewal

21-0906

11/17/21

$3,520,000.00

3rd Renewal

 

 

$5,673,800.00

Total Revised Amount

 

 

$13,127,800.00

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                          $5,673,800.00

Prime Vendor:                     GC & E Systems Group, Inc.

Prime Status:                     Non-Minority

Location:                                                               Norcross, GA

County:                                                               Gwinnett County

Prime Value:                                          $5,673,800.00 or 100.00%

 

Total Contract Value:                      $5,673,800.00 or 100.00%

Total M/FBE Value:                      $-0-

 

Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)

Exhibit 1: Contractor's Performance Report

Exhibit 2: Contract Renewal Evaluation Form

Exhibit 3: Contract Renewal Agreement No. 3

Exhibit 4: Proposed Projects - GCE FY23

 

Contact Information (Type Name, Title, Agency and Phone)
title

Lateef Ashekun, Interim CIO, Information Technology, 404-612-0192

 

Contract Attached
title

No

 

Previous Contracts
title

Yes

 

Total Contract Value

Original Approved Amount:

$1,615,000.00

Previous Adjustments:

$5,839,000.00

This Request:

$5,673,800.00

TOTAL:

$13,127,800.00


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

Funding lines to be provided by agencies requesting services (pending 2023 Budget Approval).

Key Contract Terms

Start Date: 1/1/2023

End Date: 12/31/2023

Cost Adjustment

Renewal/Extension Terms: No renewal option remains


Overall Contractor Performance Rating
: 4

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

1/1/2022

12/31/2022