Department
Real Estate and Asset Management
Requested Action
title
Request approval to utilize cooperative purchasing - Department of Real Estate and Asset Management, OMNIA Partners Contract #3341 for HVAC Products, Installation, Labor Based Solution and Related Product and Services, in the amount not to exceed $1,929,310.00 with Trane U.S. Inc. (Doraville, GA), to provide turnkey removal and replacement of existing HVAC mechanical Chiller No. 3 located in the Justice Center Complex at 185 Central Avenue, Atlanta, GA 30303. due to the unit having exhausted its useful life (32 years). Effective upon issuance of Notice to Proceed for 12 months, ending upon completion of the replacement/installation project as determined by Fulton County.
body
Requirement for Board Action
In accordance with Purchasing Code Section 102-462, requests for approval to utilize cooperative purchasing or GSA purchase contracts of more than $100,000 shall be forwarded to the Board of Commissioners for approval.
Strategic Priority Area related to this item (If yes, note strategic priority area below)
Open and Responsible Government
Commission Districts Affected
All Districts ☒
District 1 ☐
District 2 ☐
District 3 ☐
District 4 ☐
District 5 ☐
District 6 ☐
Is this a purchasing item?
Yes
Summary & Background The Fulton County Justice Center (JCC) is cooled by three (3) 900-ton chillers in the Central Energy Plant (CEP). The HVAC equipment in the CEP was installed in 1992. The life-expectancy as outlined by the American Society of Heating Refrigeration and Air-conditioning Engineers (ASHRAE) states that the average life-expectancy of this type of equipment is 23 years.
Chiller No. 3 will be replaced with a new chiller of equal size. Rather than install a 4160v machine like the existing chiller, a step-down transformer will be installed to allow for the installation of a 480v chiller that is easier to maintain. The primary chilled water pump that serves Chiller No. 3 will also be replaced as part of the project.
Scope of Work: This cooperative contract will furnish all materials, labor, tools, equipment, and appurtenances necessary to provide upgrade/ replacement of the existing HVAC mechanical equipment Chiller No. 3 to a more-high energy efficient, reliability, cost- effective and fully operational system at the Fulton County Justice Center Complex located at 185 Central Avenue, Atlanta, GA 30303.
The scope of work also includes but not limited to:
1. Mechanical Scope
Ø Replace Chiller #3.
• Cut through roof membrane to expose roof cap.
• Provide temporary weather barrier to be used while roofing membrane is removed.
• Attach lift points to roof cap.
• Disconnect and disassemble existing Chiller #3 and prepare for lift.
• Demo and remove existing 40 HP primary chilled water pump.
• Clear lift path of existing ductwork, sprinkler lines, refrigerant relief, etc.
• Install one (1) new CVHF 880-ton chiller and control valves and connect to existing chilled and condenser water piping. Chiller and control valves to be provided by Trane.
• Install new 40 HP primary chilled water pump. Pump and motor to be provided by Trane.
• Reinstall any ductwork, sprinkler lines, refrigerant relief, etc. that had been cleared from the lift path.
• Furnish and install any fittings, transitions and other materials required in replacement of chiller and pump.
• Furnish and install insulation for new pump and areas of piping were removed during replacement of chiller and pump.
• Factory start-up and commissioning.
• Replace roof membrane.
2. Electrical Scope
Ø New step-down transformer and Chiller #3 installation.
• Disconnect existing chiller from electric service.
• Disconnect existing primary chilled water pump from existing electrical service.
• Supply and deliver new transformer to job site. The transformer will need to step down the existing 4160v service to 480v for the new chiller.
• Install new transformer.
• Include all required disconnects, conduit, conductors, etc.
• Connect new chiller to new transformer.
• Connect new primary chilled water pump to existing electrical service. o Start-up and commissioning.
3. Lift Scope
Ø Roof cap, chiller, transformer, and refrigerant lift.
• Lift roof cap.
• Lift disassembled pieces of Chiller #3 from mechanical room and lower.
• Lift new chiller and set in mechanical room.
• Lift new transformer and set in mechanical room.
• Lift new refrigerant and set in mechanical room.
• Replace roof cap.
Ø Traffic control and street closure permits included.
4. Implementation Plan
Ø Expected work to occur a few weeks ahead of new Chiller system arrival
• Break up concrete slab covering the roof cap.
• Mechanical to attach lift points to roof cap.
• Cover roof hatch with temporary weather barrier
Ø New Trane Chiller system delivered to rigging company
Ø Removal and Disposal of Existing Chiller
• Electrical to disconnect existing chiller from electric service
• Mechanical and rigging to disconnect and disassemble existing Chiller #3 and prepare for lift.
• Mechanical and rigging to disconnect and disassemble existing Chiller #3 and prepare for lift
• Mechanical to clear lift path of existing ductwork, sprinkler lines, refrigerant relief, etc.
Ø Expected Lift Work to Occur on Weekend
• Rigging to deliver new Trane chiller to job site
• Electrical to deliver new transformer to job site
• Crane to lift roof cap, disassembled pieces of Chiller No. 3 from mechanical room
• Crane to lift new chiller, transformer, new refrigerant, and set in mechanical room
• Crane to replace roof cap
Ø Expected Electrical Work following the Lift Work
• Electrical to install new transformer
• Electrical to connect new chiller to new transformer
• Mechanical to install new chiller, pump, and control valves and connect to existing chilled and condenser water piping
• Mechanical to reinstall any ductwork, sprinkler lines, and refrigerant relief, etc.
• Trane to install new chiller controls
Notes: 1. All work apart from the replacement work to be performed/or completed on the weekend and preparation work and lift to occur/ or be performed during normal business hours (8am to 5pm, M-F, non-holidays)
2. Asbestos or hazardous material abatement removal shall be performed by customer
3. All existing isolation valves, disconnects, are assumed to be in working condition.
4. Proposal does not include any repairs to the only equipment in the central plant.
Community Impact: This effort is necessary for the environmental health and comfort of the patrons and employees at this County facility.
Department Recommendation: The Department of Real Estate and Asset Management recommends approval. The chiller replacement project will be managed by the Department Real Estate and Asset Management (DREAM), HVAC Maintenance Team.
The estimated time to complete the required replacement/installation is 12 months upon receipt of notice to proceed/or completion of project as determined by Fulton County and purchase order with lead time of materials and equipment.
Project Implications: This contract will allow the necessary upgrade and installation of the existing HVAC mechanical equipment to more energy efficient and reliable equipment.
Community Issues/Concerns: None that the Department is aware.
Department Issues/Concerns: If utilization of this cooperative purchasing contract is not approved, the County will not be able to provide an immediate comprehensive replacement of Chiller No. 3. A failure of this unit will seriously impact the operations of the Justice Center Complex.
Contract Modification: This is a new request
Contract & Compliance Information (Provide Contractor and Subcontractor details.)
Not Applicable
Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)
Exhibit 1: OMNIA Partners Contract #3341
Exhibit 2: Cost Proposal
Exhibit 3: Performance Evaluation
Contact Information (Type Name, Title, Agency and Phone)
title
Joseph N. Davis, Director, Department of Real Estate and Asset Management, (404) 612-3772
Contract Attached
title
Yes
Previous Contracts
title
Yes
Total Contract Value
Original Approved Amount: |
$0.00 |
Previous Adjustments: |
$0.00 |
This Request: |
$1,929,310.00 |
TOTAL: |
$1,929,310.00 |
Fiscal Impact / Funding Source
Funding Line 1:
500-520-5200-ACJC Phase: 500EQM, Major Program: EQUIP Justice Tower Chiller- $1,929,310.00
Key Contract Terms |
Start Date: Upon BOC Approval |
End Date: Effective upon issuance of Notice to Proceed for 12-months or completion of replacement/ installation project as determined by Fulton County |
Cost Adjustment: |
Renewal/Extension Terms: |
Overall Contractor Performance Rating: 79
Would you select/recommend this vendor again?
Yes
Report Period Start: |
Report Period End: |
10/1/2024 |
12/31/2024 |