Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title
Accept and file the Fulton County Capital Program Quarterly Update for the period October 1, 2020 - December 31, 2020
body
Requirement for Board Action (Cite specific Board policy, statute or code requirement)
Report as requested by the Board of Commissioners
Strategic Priority Area related to this item (If yes, note strategic priority area below)
Open and Responsible Government
Summary & Background (First sentence includes Agency recommendation. Provide an executive summary of the action that gives an overview of the relevant details for the item.)
Scope of Work: During the June 5, 2002 Board of Commissioners meeting (Item #02-0642), the Board requested a quarterly status report on large construction and/or professional services contracts. The program and construction management contracts are included by specific request of the Board.
The attached report is provided as part of the quarterly project report.
The following are the capital budget values established for each of the respective projects.
|
• DREAM Construction Projects |
$1,229,515.00 |
|
• FCURA (Urban Redevelopment Bond Fund) Phase I |
$90,000,000.00 |
|
• Libraries (Phase II) |
$47,367,000.00 |
|
• Public Works |
$374,107,354.00 |
|
• Wayfinding |
$3,089,937.00 |
|
Total |
$515,793,806.00 |
Community Impact: Countywide
Department Recommendation: Accept and file the Fulton County Capital Program Quarterly Update for the period of October 1, 2020 - December 31, 2020
Project Implications: None
Community Issues/Concerns: None
Department Issues/Concerns: None
History of BOC Agenda Item: During the June 5, 2002 Board of Commissioners meeting (Item #02-0642), the Board requested a quarterly status report on large construction and/or professional services contracts. The program and construction management contracts are included by specific request of the Board. The Capital Program Quarterly Update is submitted for informational purposes.