Department
Public Works
Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title
Request approval of a Contract Item Agreement (CIA) between Fulton County and the Georgia Department of Transportation (GDOT) for water main relocations associated with the widening and improvements to Abbotts Bridge Road (SR 120)-Promise Parkway to Boles Road, Project P.I. No. 721000, in Johns Creek, Georgia, in an estimated amount of $2,426,610.00.
body
Requirement for Board Action (Cite specific Board policy, statute or code requirement)
GA CONST Art. 9, § 3, ¶ I provides that the County may contract for any period not exceeding 50 years with any other public agency, public corporation, or public authority for joint services, for the provision of services, or for the joint or separate use of facilities or equipment; but such contracts must deal with activities, services, or facilities that the contracting parties are authorized by law to undertake or provide. Also, O.C.G.A § 36-10-1 states that all official contracts entered into by the County governing authority with other persons on behalf of the County shall be in writing and entered on its minutes.
Strategic Priority Area related to this item (If yes, note strategic priority area below)
Health and Human Services
Commission Districts Affected
All Districts ☐
District 1 ☒
District 2 ☐
District 3 ☐
District 4 ☐
District 5 ☐
District 6 ☐
Is this a purchasing item?
No
Summary & Background (First sentence includes Agency recommendation. Provide an executive summary of the action that gives an overview of the relevant details for the item.)
Scope of Work: The Georgia Department of Transportation (GDOT) is planning improvements to Abbotts Bridge Road (SR 120) between Promise Parkway and Boles Road in Johns Creek. The project will include roadway widening and several intersection upgrades, including turn lanes, landscaped medians, and sidewalk enhancements. As part of this work, approximately 7,225 linear feet of 10‑inch water main and associated appurtenances will need to be relocated within the existing right‑of‑way. Water service to customers will remain uninterrupted throughout the construction period. GDOT intends to bid the roadway improvements in mid‑2026 and has requested execution of a Contract Item Agreement (CIA) with Fulton County to allow GDOT to include the water main relocation work in its bid package. Following award of the construction contract, Fulton County will reimburse GDOT for the actual water main relocation costs in accordance with the CIA. Fulton County staff will be on-site during the relocation to ensure all work meets County standards. The estimated cost for the relocation and installation of the impacted water mains is $2,426,610.00. Funding has been budgeted through the Water and Sewer Fund and is included in the 2026 - 2030 Capital Improvement Program.
Community Impact: Fulton County currently operates 10‑inch and 8‑inch water mains serving properties along Abbotts Bridge Road (SR 120). The planned road improvements will impact these existing water lines, which provide service to developments in the area and support the water distribution system supplying the City of Johns Creek.
Department Recommendation: The Department of Public Works believes that the most cost‑effective approach to completing the water main relocations is to allow the Georgia Department of Transportation (GDOT) to include the work in its roadway project bid. Therefore, Public Works recommends that Fulton County enter into a Contract Item Agreement (CIA).
Project Implications: The road improvements will impact the existing water mains due to grade modifications and roadway widening along Abbotts Bridge Road (SR 120), which require the relocation of water mains and the adjustment of valves to match the proposed roadway surface. These relocations are necessary to maintain uninterrupted water service in the area.
Community Issues/Concerns: During construction of the relocations, water service will be maintained, although temporary interruptions may be necessary during tie‑ins to the existing and newly installed water mains.
Department Issues/Concerns: The Public Works Department is not aware of any issues or concerns with this proposed Contract Item Agreement (CIA).
Contract Modification
New Procurement
Contract & Compliance Information (Provide Contractor and Subcontractor details.)
Georgia Department of Transportation (GDOT)
Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)
EXHIBITS-A PI 721000-Fulton County W&S Contract Item Agm Pkg
Contact Information (Type Name, Title, Agency and Phone)
title
Georgia Department of Transportation (GDOT)
Contract Attached
title
Yes
Previous Contracts
title
No
Total Contract Value
|
Original Approved Amount: |
|
|
Previous Adjustments: |
|
|
This Request: |
$2,426,610.00 |
|
TOTAL: |
$2,426,610.00 |
Grant Information Summary
|
Amount Requested: |
|
☐ |
Cash |
|
Match Required: |
|
☐ |
In-Kind |
|
Start Date: |
|
☐ |
Approval to Award |
|
End Date: |
|
☐ |
Apply & Accept |
|
Match Account $: |
|
|
|
Fiscal Impact / Funding Source
Funding Line 1:
Water and Sewer R & E Fund, 203-540-5400-I301