File #: 24-0802    Version: 1 Name:
Type: CM Action Item - Health and Human Services Status: Passed
File created: 10/31/2024 In control: Board of Commissioners
On agenda: 11/20/2024 Final action: 11/20/2024
Title: Request approval to extend an existing Contract - Public Works Department, 17RFP031617K-DJ, Progressive Design/Build Services for the Big Creek Water Reclamation Facility (WRF) Expansion Project Phase 2B with Archer Western-Brown and Caldwell Joint Venture (Atlanta, GA) in an amount not to exceed $279,436.22, utilizing the Owner's Contingency to address additional work required and to extend the contract through March 21, 2025. Effective upon BOC approval.
Attachments: 1. Exhibit 1 Extension To Contract #5, 2. Exhibit 2 Performance Evaluation

 

Department

Public Works

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval to extend an existing Contract - Public Works Department, 17RFP031617K-DJ, Progressive Design/Build Services for the Big Creek Water Reclamation Facility (WRF) Expansion Project Phase 2B with Archer Western-Brown and Caldwell Joint Venture (Atlanta, GA) in an amount not to exceed $279,436.22, utilizing the Owner’s Contingency to address additional work required  and to extend the contract through March 21, 2025. Effective upon BOC approval.

 

body

Requirement for Board Action (Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Health and Human Services

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background: The current contract structure between Fulton County and the Joint Venture (JV) requires the Public Works Department to obtain BOC approval for all spending increases beyond the previously approved GMP (Guaranteed Maximum Price).  This includes use of the project’s Owner Contingency funds. Upon approval the Public Works Department will allocate these contingency funds to cover all costs associated with this action. Additionally, the Public Works Department is seeking a time extension 03/21/2025 to complete the work that is outlined. 

 

Scope of Work: The Public Works Department is seeking the approval to utilize the Owner’s Contingency within the contract to address the following five (5) items:                                                                                                      

 

Item

Scope of Work Description

Cost & Time Impact

1

Installation of signage and building names throughout the facility. This item is a life safety requirement.

115,126.60

2

SCADA upgrades for improved graphic and background displays on HMI’s for the primary clarifiers, grit classifiers, wash compactors, BNR anaerobic tanks, fine screens.  This item includes upgraded alarming setups, additional symbol creation.

$33,167.09 @ 6 Weeks

3

Additional monitors and associated equipment to provide plant operators with additional information within the control room and redundant server location.

$62,026.99 @ 8 weeks

4

Upgrade and redundancy of CCTV system within the Maintenance Building. This will allow operators to monitor the CCTV feed from the Maintenance Building

$27,515.96 @ 6 weeks

5

Electrical system upgrades. This item includes the replacement of circuit breakers, covers the costs for an electrical coordination study, and MCC testing during planned outages.

$41,599.58 @ 6 weeks

 

These items were not included in the original GMP for the project, however since the project has continued to be completed within budget, the remaining balance of the owner’s contingency is sufficient to cover these expenses.  All of these elements will allow for improvements to the plant’s operation and safety of the facility.

This change order does not include any additional compensation that may be owed to the Joint Venture to cover costs associated with extended overheads, time-critical general conditions, heavy equipment, and engineering services during construction associated with this contract extension.  These costs will be evaluated during the coming months by Fulton County and the Joint Venture and will be included in a project close-out change order, if necessary.  

 

Community Impact: No immediate impact to the community is expected from this item.

 

Department Recommendation: The Public Works Department recommends approval of this item.

 

Project Implications: Approval of this item will enable the Joint Venture to implement critical improvements that address life safety requirements, enhance electrical protections, and support operational upgrades.

 

Community Issues/Concerns: No Community issues/concerns have been noted

 

Department Issues/Concerns: The Public Works Department has not identified any concerns/issues with this request. 

 

Contract Modification

Current Contract History

BOC Item

Date

Dollar Amount

Original Award (Phase 1A)

17-0795

10/4/2017

$1,599,500.00

Original Award (Phase 1B)

18-0372

6/6/2018

$18,450,543.00

Original Award (Phase 2A)

19-0540

7/10/2019

$16,932,220.00

Original Award  (Phase 2B)

20-0476

7/8/2020

$274,768,712.00

Change Order 1 (Phase 1B)

20-0471

6/17/2020

$554,344.00

Change Order 1 (Phase 2B)

22-0661

9/21/2022

$259,128.00

Change Order 2 (Phase 2B)

23-0075

2/1/2023

$339,444.13

Change Order 3 (Phase 2B)

24-0078

1/10/2024

$759,719.88

Change Order 4 (Phase 2B)

24-0442

6/26/2024

$3,782,603.00

Change Order 5 (Phase 2B)

 

 

$279,436.22

Total Revised Amount

 

 

$317,725,650.23

 

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                          $279,436.22

 

Prime Vendor:                                          Archer Western/Brown and Caldwell (JV Partners                                                                                                                               50/50JV Both firms Non- Minority)

Prime Status:                                          Non-Minority

Location:                                                               Atlanta, GA

County:                                                               Fulton County  

Prime Value:                                          $41,915.43 or 15.00%

 

Subcontractor:                                Image 360

Subcontractor Status:      Non-Minority

Location:                                                     Marietta, GA

County:                                                      Cobb County

Contract Value:                               $95,008.31 or 34.00%

 

Subcontractor:                                Excel Electrical  

Subcontractor Status:      Non-Minority

Location:                                                     Kennesaw GA

County:                                                      Cobb County

Contract Value:                               $67,064.69 or 24.00%

 

Subcontractor:                                          Global Control  

Subcontractor Status:      Asian American Female Business Enterprise

Location:                                                     Alpharetta, GA

County:                                                      Fulton County

Contract Value:                               $75,447.78 or 27.00%

 

Total Contract Value:                     $279,436.22 or 100.00%

Total Certified Value:                     $75,447.78 or 27.00%

 

Exhibits Attached

Exhibit 1: Contract to Form Extension #5

Exhibit 2: Performance Evaluation

 

Contact Information (Type Name, Title, Agency and Phone)
title

David E. Clark, Director, Public Works 404-612-2804

 

Contract Attached
title

Yes


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$311,750,975.00

Previous Adjustments:

$5,695,239.01

This Request:

$279,436.22

TOTAL:

$317,725,650.23


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

235-540-5400-S157: W&S Construction-2020, Public Works, Big Creek Plant Expansion

 

Key Contract Terms

Start Date: Upon BOC Approval

End Date: 3/21/2025

Cost Adjustment: $0.00

Renewal/Extension Terms: March 21, 2025


Overall Contractor Performance Rating: 91

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

9/17/2024

10/7/2024