File #: 21-0973    Version: 1 Name:
Type: CM Action Item - Health and Human Services Status: Passed
File created: 10/12/2021 In control: Board of Commissioners
On agenda: 12/1/2021 Final action: 12/1/2021
Title: Request approval to extend an existing contract - Department of Public Works, FAA Contract #DTFAWA-15-C000018, Air Traffic Control Services - Night Coverage at Fulton County Executive Airport Brown-Field in the amount not to exceed $252,936.00 with Robinson Aviation, Inc. (RVA) (Oklahoma, OK), to provide air traffic control night coverage services at Fulton County Executive Airport - Charlie Brown Field for an additional 12 month period. Effective dates: January 1, 2022 through December 31, 2022. (APPROVED)
Attachments: 1. Exhibit 1: Extension No. 2 to Form of Contract, 2. Exhibit 2: Contractor Performance Report, 3. 2021-0973

 

Department

Public Works

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval to extend an existing contract - Department of Public Works, FAA Contract #DTFAWA-15-C000018, Air Traffic Control Services - Night Coverage at Fulton County Executive Airport Brown-Field in the amount not to exceed $252,936.00 with Robinson Aviation, Inc. (RVA) (Oklahoma, OK), to provide air traffic control night coverage services at Fulton County Executive Airport - Charlie Brown Field for an additional 12 month period. Effective dates: January 1, 2022 through December 31, 2022.  (APPROVED)

body


Requirement for Board Action
(Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract & necessary for completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Infrastructure and Economic Development

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background: Department of Public Works recommends approval to extend existing contract with Robinson Aviation, Inc. (RVA) to provide air traffic control night coverage services at Fulton County Executive Airport - Charlie Brown Field.

 

Scope of Work: The air traffic control tower located at the Fulton County Executive Airport - Charlie Brown Field is manned by air traffic controllers 24 hours a day to serve the general aviation aircraft landing and taking off from the Airport. The Federal Aviation Administration (FAA) contracts directly with Robinson Aviation, Inc. (RVA) to provide 16 hours of daytime air traffic control services through contract #DTFAWA-15 C000019. This contract will be renewed by the FAA during the first quarter of 2022.

 

Fulton County has traditionally funded the 8 hours of night service not covered by the FAA through a separate contract between Fulton County and RVA. This contract was extended by the BOC on November 6, 2019 to cover the night coverage through December 31, 2021. This request is to extend the contract for the period of January 1, 2022 through December 31, 2022 to ensure uninterrupted night time coverage.  

 

Community Impact: No impacts are anticipated within the community based on this contract extension.

 

Department Recommendation: Department of Public Works recommends approval to extend existing contract to provide air traffic control night coverage services at the Fulton County Executive Airport - Charlie Brown Field.

 

Project Implications: The FAA assures the Air Traffic Control Tower provides safe, orderly and expeditious movement of air traffic in the vicinity of and on the movement area of the Fulton County Airport. The Airport Enterprise Fund has traditionally paid the added costs associated with night coverage to allow for 24-hour coverage at the airport. No other metro Atlanta airport, with the exception of Hartsfield-Jackson, provides 24-hour coverage at their control towers.

 

Community Issues/Concerns: None has been raised to Public Works staff.

 

Department Issues/Concerns: The department has no issues/concerns as long as the current contract can be extended while we await final direction from the FAA.

 

Contract Modification

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

15-0987

11/4/2015

$205,680.00

1st Renewal

16-1114

12/7/2016

$209,793.60

2nd Renewal

17-0748

9/13/2017

$213,989.47

3rd Renewal

18-0747

10/17/2018

$220,409.15

Amendment No. 1

19-0084

2/6/2019

$ 10,973.85

4th Renewal

19-0902

11/6/2019

$241,493.00

Extension No. 1

20-0765

10/21/2020

$280,881.00

Extension No. 2

 

 

$ 252,936.00

Total Revised Amount

 

 

$1,636,156.07

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                          $252,936.00

 

Prime Vendor:                     Robinson Aviation, Inc., RVA

Prime Status:                     Non-Minority

Location:                                                               Oklahoma City, OK

County:                                                               Oklahoma County

Prime Value:                                          $48,057.84 or 19.00%

 

 

Subcontractor:                                          C12 Aviation, Inc.

Subcontractor Status:                     African American Female Business Enterprise- Non-Certified

Location:                                                               Dunwoody, GA

County:                                                               DeKalb County

Contract Value:                                          $204,878.16 or 81.00%

 

Total Contract Value:                     $252,936.00 or 100.00%

Total M/FBE Value:                     $204,878.16 or 81.00%

 

Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)

Exhibit 1: Extension No.2 to Form of Contract

Exhibit 2: Contractor Performance Report

Contact Information (Type Name, Title, Agency and Phone)
title

Tim Beggerly, Airport Manager, Public Works 404-613-4203

 

Contract Attached
title

No


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$   205,680.00

Previous Adjustments:

$1,177,540.07

This Request:

$   252,936.00

TOTAL:

$1,636,156.07


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

200-540-5601-1160: Airport, Public Works, Professional Services - $252,936.00

Key Contract Terms

Start Date: 1/1/2022

End Date: 12/31/2022

Cost Adjustment:

Renewal/Extension Terms: none


Overall Contractor Performance Rating: 4.0

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

1/1/2021

6/30/2021