File #: 24-0442    Version: 1 Name:
Type: CM Action Item - Health and Human Services Status: Passed
File created: 4/22/2024 In control: Board of Commissioners
On agenda: 6/26/2024 Final action: 6/26/2024
Title: Request approval of a change order less than 10% - Public Works, 17RFP031617K-DJ Progressive Design/Build Services for Big Creek Water Reclamation Facility (WRF) Expansion Project Phase 2B in the amount of $3,782,603.00 with Archer Western-Brown and Caldwell Joint Venture (Atlanta, GA) to cover costs associated with tariffs for equipment/material purchases and overall improvements to the project site and existing administration building and to extend the contract for an additional 30 days to the contract days to allow for completion of these items. Effective upon BOC approval. (APPROVED)
Attachments: 1. Exhibit #1: CHANGE ORDER NO.4 Form of Contract, 2. Exhibit 2: CPR-Evaluation ArcherWest/BC JV, 3. 2024-0442

 

Department

Public Works

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval of a change order less than 10% - Public Works, 17RFP031617K-DJ Progressive Design/Build Services for Big Creek Water Reclamation Facility (WRF) Expansion Project Phase 2B in the amount of $3,782,603.00 with Archer Western-Brown and Caldwell Joint Venture (Atlanta, GA) to cover costs associated with tariffs for equipment/material purchases and overall improvements to the project site and existing administration building and to extend the contract for an additional 30 days to the contract days to allow for completion of these items. Effective upon BOC approval.  (APPROVED)

body


Requirement for Board Action
(Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Choose an item.

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background The current structure of the contract between the Fulton County and the Joint Venture (JV) requires that the Public Works Department seek BOC approval for all spending increases over the previously approved GMP (Guaranteed Maximum Price).  This includes utilization of the project’s Owner Contingency.  If approved, the Public Works Department will use these contingency funds to cover all costs within this action. In addition, the Public Works Department is seeking an extension of 30 days to the end of contract to allow for the completion of the activities as outlined within this item.

 

Scope of Work: The Public Works Department is seeking the approval to utilize the Owner’s Contingency within the contract for the four (4) following items:                               

 

 

Item

Scope of Work Description

Cost

1

Demolition of existing aerobic digestor foundation and under slab piping. It expected this activity can be accomplished within 30 calendar days.

$322,353.00

2

Removal of grit and wastewater from digestors ahead of demolition.

$1,314,625.00

3

Administration Building window replacement and store front upgrades.

$24,076.00

4

Tariffs including claims for the following material/services: (a) reinforcement steel escalation in the amount of $139,385.40  (b)  Carbon media and RFP (reinforced fiber-glass piping) price escalations with ECS Environmental in the amount of $849,782.31 (c) stainless steel price escalations in the amount of $411,926.94 (d) structural steel/miscellaneous metal price escalations in the amount of $ $298,302.14(e) Grier Trucking escalations in the amount of $ 35,952.00, (f) material escalations for Ovivo, USA in the amount of $158,392.50, and (g) reinforced fiberglass piping with Enduro in the amount of $227,807.58. 

$2,121,549.00

The funds for these elements are included within the Owner’s Contingency for the project and no additional funds are being requested as part of this item. 

 

Community Impact: No direct impact to the community is expected from these items.

 

Department Recommendation: The Department of Public Works recommends approval of this item.

 

Project Implications: Approval of this item will allow the Joint Venture to address price escalations/tariff costs incurred by subcontractors and other vendors on the project. It will also allow the site to be fully prepared for any future needs. 

 

Community Issues/Concerns: No community issues/concerns have been noted.

 

Department Issues/Concerns: The Public Works Department has not identified any concerns/issues with this request.

 

Contract Modification

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

20-0476

7/8/2020

$274,768,712.00

Change Order #1

22-0661

9/21/2022

$259,128.00

Change Order #2

23-0075

2/1/2023

$339,444.13

Change Order #3

24-0078

1/10/2024

$759,719.88

Change Order #4

 

 

$3,782,603.00

Total Revised Amount

 

 

$279,909,607.01

 

 

 

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                          $3,782,603.00

 

Prime Vendor:                     Archer Western/Brown and Caldwell (JV Partners 50/50JV (Both firms Non- Minority)

Prime Status:                     Non-Minority

Location:                                                               Atlanta, GA

County:                                                               Fulton County  

Prime Value:                                          $2,347,744.86 or 62.07%

 

Subcontractor:                                Anatek, Inc.  

Subcontractor Status:      Hispanic Female Business Enterprise -Certified

Location:                                                     Marietta, GA

County:                                                      Cobb County

Contract Value:                               $115,500.00 or 3.05%

 

Subcontractor:                                Cowart Industrial Services  

Subcontractor Status:      Non-Minority

Location:                                                     Carrollton, GA

County:                                                      Carroll County

Contract Value:                               $1,044,500.00 or 27.61%

 

Subcontractor:                                          Diamond Glass Company 

Subcontractor Status:      Non-Minority

Location:                                                     Alpharetta, GA

County:                                                      Fulton County

Contract Value:                               $24,076.00 or 0.64% 

 

Subcontractor:                                Grier Trucking

Subcontractor Status:      African American Male Business Enterprise - Certified

Location:                                                     Atlanta, GA

County:                                                      Fulton County

Contract Value:                               $33,600.00 or 0.89%

 

Subcontractor:                                SSD Contracting

Subcontractor Status:      Hispanic Male Business Enterprise - Certified

Location;                     Chamblee, GA

County:                                                                       DeKalb County

Contract Value:                               $217,182.14 or 5.74%

 

Total Contract Value:                     $3,782,603.00 or 100.00%

Total Certified Value:                     $366,282.14 or 9.68%

 

Exhibits Attached:

Exhibit 1: Change Order

Exhibit 2: Contractor’s Performance Report

 

Contact Information
title

David E. Clark, Director, Public Works 404-612-2804

 

Contract Attached
title

Yes


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$274,768,712.00

Previous Adjustments:

$1,358,292.01

This Request:

$3,782,603.00

TOTAL:

$279,909,607.01


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

235-540-5400-S157:  W&S Construction-2020, Public Works, Big Creek Plant Expansion, $3,782,603.00

 

Key Contract Terms

Start Date: BOC Approval

End Date: 9/6/2024

Cost Adjustment: $3,782,603.00

Renewal/Extension Terms: 30 Days


Overall Contractor Performance Rating: 82

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

3/12/2024

5/13/2024