Title: Request approval of a change order of less than 10% - Fulton County Library System, 22RFP040222K-CRB, Design/Build Services for the Martin Luther King, Jr. Library Renovation, for the Library Capital Improvement Program, Phase II (FCLS-CIP), in an amount not to exceed $54,257.00 with Albion General Contractors, Inc. (Sandy Springs, GA), to amend existing contract for additional funding due to escalation in construction costs for the Design/Build services for the renovation project for the Martin Luther King, Jr. Library. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
Attachments: 1. Exhibit 1 Change Order No. 1 to Form of Contract- Albion, 2. Exhibit 2 Change Order Proposal- MLK Library Expansion Pricing, 3. Exhibit 3 Contractor's Performance Report - Albion, 4. 2023-0854
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Department

Library

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval of a change order of less than 10% - Fulton County Library System, 22RFP040222K-CRB, Design/Build Services for the Martin Luther King, Jr. Library Renovation, for the Library Capital Improvement Program, Phase II (FCLS-CIP),  in an amount not to exceed $54,257.00 with Albion General Contractors, Inc. (Sandy Springs, GA), to amend existing contract for additional funding due to escalation in construction costs for the Design/Build services for the renovation project for the Martin Luther King, Jr. Library.  Effective upon BOC approval.  (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)     

body

 

Requirement for Board Action (Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Arts and Libraries

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background Request approval of Change Order No. 1 to amend the existing contract for additional funding due to escalation in construction costs for the Design/Build Services for the Martin Luther King, Jr. Library renovation project.

 

Scope of Work: Modify existing contract for additional funding due to escalation in construction costs submitted by Albion General Contractors, Inc. to provide Design/Build Services through all phases of design and construction for the renovation of the approximately 4,100 sq. ft. Martin Luther King, Jr. Library.   This construction cost increase occurred after the renovation project was budgeted.

 

Though these additional costs are specific to the renovation project for the Martin Luther King, Jr. Library, they are representative of inflationary price escalations, delays in equipment and materials deliveries, and labor shortages now seen throughout the construction industry. 

 

This Change Order for additional funding is necessary to prevent the disruption in the process and enable the completion of construction for the renovation project for the Martin Luther King, Jr. Library.

 

Community Impact: This effort is necessary for the renovation of the library in the old 4th Ward community of Atlanta, GA.  The successful completion of the construction on this library will impact nearby communities as well as communities throughout Fulton County.

 

Department Recommendation: The Library recommends approval of Change Order less than 10% modifying the existing contract for additional funding for the Design/Build services for renovation for the Martin Luther King, Jr. Library.

 

Project Implications: This contract intent is to restore the designated, existing facility, economically and efficiently, to a condition which is fully functional to meet the long-term space and services needs of the constituents and employees of Martin Luther King, Jr. Library. The cost of the requested service will be funded using Library Bond Funds; therefore, it will not impact the County or Library operations.

 

Community Issues/Concerns: None of which the Department is aware.

 

Department Issues/Concerns: If this change order is not approved, there may be a potential disruption and delay in performing the Design/Build services for renovation project of the MLK Library.

 

Contract Modification

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

22-0871

11/16/22

$675,875.00

Change Order No. 1

 

 

$54,257.00

Total Revised Amount

 

 

$730,132.00

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                           $54,257.00

 

Prime Vendor:                     Albion General Contractors, Inc.

Prime Status:                     Small Business Enterprise (SBE)

Location:                     Sandy Springs, GA

County:                                                               Fulton County

Prime Value:                                          $54,257.00 or 100.00%

 

Total Contract Value:                     $54,257.00 or 100.00%

Total Certified Value:                     $54,257.00 or 100.00%

 

Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)

Exhibit 1: Change Order No. 1 to Form of Contract

Exhibit 2: Change Order Proposal

Exhibit 3: Contractor’s Performance Report

 

Contact Information (Type Name, Title, Agency and Phone)
title

Joseph N. Davis, Director, Department of Real Estate and Asset Management, (404) 612-3772

 

Contract Attached
title

Yes


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$675,875.00

Previous Adjustments:

$0.00

This Request:

$54,257.00

TOTAL:

$730,132.00


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

573-650-6500-L011: Library Bond Capital Phase 2, Library, Central Library- $15,074.91

Funding Line 2:

573-650-6500-L017: Library Bond Capital Phase 2, Library, Cleveland Ave Library -$357.69

Funding Line 3:

573-650-6500-L034: Library Bond Capital Phase 2, Library, East Point Library- $6,121.75

Funding Line 4:

573-650-6500-L035: Library Bond Capital Phase 2, Library, Fairburn Hobgood Palmer Library- $1,176.14

Funding Line 5:

573-650-6500-L036: Library Bond Capital Phase 2, Library, Hapeville Library- $3,136.74

Funding Line 6:

573-650-6500-L039: Library Bond Capital Phase 2, Library, East Point Library- $28,389.77

Key Contract Terms

Start Date: Effective upon BOC approval

End Date: Completion of construction project as determined by Fulton County

Cost Adjustment

Renewal/Extension Terms: N/A


Overall Contractor Performance Rating: 82

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

7/1/2023

9/30/2023