File #: 23-0773    Version: 1 Name:
Type: CM Action Item - Open & Responsible Government Status: Passed
File created: 9/27/2023 In control: Board of Commissioners
On agenda: 11/1/2023 Final action: 11/1/2023
Title: Request approval to increase spending authority - Department of Real Estate and Asset Management, 21ITB131067C-GS, On-Site Door Repair and Overhead Door Preventive and Predictive Maintenance Countywide in an amount not to exceed $57,464.00 with Overhead Door Company of Atlanta, dba D.H. Pace Company, Inc. (Atlanta, GA) to cover the costs to complete the on-going replacement/emergency repair projects for on-site door repair services at several Fulton County facilities for FY2023. Effective upon BOC approval. (APPROVED)
Attachments: 1. Exhibit 1 Amendment No. 2 to Form of Contract, 2. Exhibit 2 Cost Proposals - Central Fulton, 3. Exhibit 2 Cost Proposals - Greater Fulton, 4. Exhibit 3 Contractor's Performance Report - D H Pace & Piedmont, 5. 2023-0773

 

Department

Real Estate and Asset Management

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval to increase spending authority - Department of Real Estate and Asset Management, 21ITB131067C-GS, On-Site Door Repair and Overhead Door Preventive and Predictive Maintenance Countywide in an amount not to exceed $57,464.00 with Overhead Door Company of Atlanta, dba D.H. Pace Company, Inc. (Atlanta, GA) to cover the costs to complete the on-going replacement/emergency repair projects for on-site door repair services at several Fulton County facilities for FY2023. Effective upon BOC approval.  (APPROVED)

body

 

Requirement for Board Action (Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Open and Responsible Government

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background: This request is to increase spending authority to cover the costs for some of the on-going replacement and emergency repair projects for on-site door repair services at several identified Fulton County facilities for FY2023.

 

Scope of Work: This contract furnishes all materials, labor, tools, equipment, and appurtenances necessary to provide on-site door repair and preventive and predictive maintenance services Countywide. The scope of work includes inspection and repair of doors and mountings, wind locks, guides weather stripping, counterbalance and to inspect all pivot points, hinges latches, center roller supports and maintenance repair and replacement on a case-by case basis. Preventive and/or Predictive Maintenance (PM) checks include, but are not limited to:

 

                     Visual and Audible Inspection

                     Operations Check

                     Roll-Up doors: Manual and Power Operated

                     Swing Doors, ADA equipped Doors and Main Entrance

                     Gates with Secured Access

                     Fire doors and Fire Curtains

                     Maintenance Services on Electromagnetic Devices when Necessary

                     Repair and Replacement on Case-by-Case Basis

 

The Costs Breakdown for these identified Fulton County facilities:

 

Greater Fulton Area (5220):

 

 

County Facility

 Project Description

Project Cost

1

Central Maintenance Facility

Remove, furnish, and install new one (1) Concrete Pad for new Operator Front Entrance Gate

$11,631.00

 

 

Remove, furnish, and install one (1) new 610 Series Existing Rolling Steel Door   

$12,856.00

2

Sheriff Fleet Division Warehouse

Remove and replace two (2) Front and Side Entrance Doors                         

$8,235.00

4

Washington Park Library

Furnish and install one (1) Custom  Sized Piece of Insulated Glass at  Front Entrance                                      

$7,990.00

5

College Park Library

Furnish and install three (3) SOC HD Cap Screw

$1,050.00

 

Increase Total

 

$41,762.00

 

Central Fulton Area (5221):

 

County Facility

Project Description

Project Cost

1

Fulton County Jail Complex

Repair Small Sally Port Entrance & Exit

$4,917.00

2

Front Main H & H Building

Furnish and install two (2) Rodent Proof Door Sweeps and one (1) Vertical Door Seal                        

$1,475.00

4

Government Center Tower Building

Furnish and install two (2) Closers and three (3) Bail Bearing Hinges                                         

$2,810.00

5

Government Center Assembly Building

Furnish and install one (1) Overhead Concealed Closer with Special Spindle

$6,500.00

 

Increase Total

 

$15,702.00

 

Community Impact: This contract impacts the community in having the ability to provide on-site doors repairs and maintenance services on Countywide facilities.

 

Department Recommendation: The Department of Real Estate and Asset Management recommends approval.

 

The requested increase in the total amount of $57,464.00 will allow the completion of remaining on-going replacement/emergency repair projects and enough spending authority to cover the cost for PM services for the remainder of FY2023.  We have almost exhausted D. H. Pace Company, Inc. approved spending authority ($150,000.00) for FY2023, and this is not sufficient to maintain and to provide on-site door repair and preventive and predictive maintenance services Countywide.

 

The project management is coordinated by the Department of Real Estate and Asset Management Building Maintenance Teams from Greater (5220) and Central (5221) Fulton.

 

 

Project Implications: This contract ensures safety and security of employees and citizens. In many cases structural integrity of facilities will be compromised leading to vandalism and theft in County-owned facilities. Not having a professional contractor could also result in the County's failure to comply with Federal ADA requirements.

 

Community Issues/Concerns: None of which the Department is aware.

 

Department Issues/Concerns: If this increase spending authority is not approved, there will be a delay in completing the on-going maintenance and door replacement/repair projects, and regular routine preventive maintenance repairs for the remainder of FY2023.

 

Contract Modification

 

(A)                     Overhead Door Company of Atlanta dba D. H. Pace Company, Inc.

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

22-0057

1/19/22

$170,000.00

Increase Spending Authority No. 1

22-0743

10/5/22

$30,000.00

1st Renewal

22-0731

10/5/22

$150,000.00

Increase Spending Authority No. 2

 

 

$57,464.00

Total Revised Amount

 

 

$407,464.00

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                          $57,464.00

 

Prime Vendor:                     Overhead Door Company of Atlanta dba D.H. Pace Company, Inc.

Prime Status:                     Non-Minority

Location:                                                               Atlanta, GA

County:                                                               Fulton County

Prime Value:                                          $57,464.00 or 100.00%

 

Total Contract Value:                     $57,464.00 or 100.00%

Total Certified Value:                     $0.00 or 0.00%

 

Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)

Exhibit 1:  Amendment No. 2 to Form of Contract

Exhibit 2:  Cost Proposals

Exhibit 3:  Contractor’s Performance Report

 

Contact Information (Type Name, Title, Agency and Phone)
title

Joseph N. Davis, Director, Department of Real Estate and Asset Management, (404) 612-3772

 

Contract Attached
title

Yes


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$170,000.00

Previous Adjustments:

$180,000.00

This Request:

$57,464.00

TOTAL:

$407,464.00


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

100-520-5220-1116: General, Real Estate and Asset Management, Building Maintenance - $ 41,762.00

 

Funding Line 2:

100-520-5221-1116: General, Real Estate and Asset Management, Building Maintenance - $ 15,702.00

Key Contract Terms

Start Date: Upon BOC Approval

End Date:  12/31/2023

Cost Adjustment

Renewal/Extension Terms: N/A


Overall Contractor Performance Rating: 79

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

4/1/2023

6/30/2023