Title: Request approval to amend an existing contract - Department of Real Estate and Asset Management, 24RFP072424K-JA, Program Management and Professional Services for the Fulton County Jail Capital Improvement Program Phase II, in an amount not to exceed $5,130,235.02 with ACR Partners, a joint venture comprised of AECOM Technical Services, Inc. (AECOM), Comprehensive Program Services (CPS) and H.J. Russell & Company (HJR) (Atlanta, GA) to increase the spending authority for Year 2 of the initial 5-Year contract and to amend the original scope of work in Phase II to provide comprehensive program management and professional services for the construction of an interim 600-bed modular housing facility located on the existing Rice St. jail campus. Effective upon BOC approval. (APPROVED)
Attachments: 1. Exhibit 1 - Amendment No. 1 to Form of Contract- PMT Fulton County Jail CIP with ACR Partners, 2. Exhibit 2 - Cost Proposal (1), 3. Exhibit 3 - Performance Evaluation - ACR (1)

 

Department

Real Estate and Asset Management

 

Requested Action

title

 

Request approval to amend an existing contract - Department of Real Estate and Asset Management, 24RFP072424K-JA, Program Management and Professional Services for the Fulton County Jail Capital Improvement Program Phase II, in an amount not to exceed $5,130,235.02 with ACR Partners, a joint venture comprised of AECOM Technical Services, Inc. (AECOM), Comprehensive Program Services (CPS) and H.J. Russell & Company (HJR) (Atlanta, GA) to increase the spending authority for Year 2 of the initial 5-Year contract and to amend the original scope of work in Phase II to provide comprehensive program management and professional services for the construction of an interim 600-bed modular housing facility located on the existing Rice St. jail campus. Effective upon BOC approval.  (APPROVED)

body

 

Requirement for Board Action

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item

Open and Responsible Government

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background: The current agreement between Fulton County and the City of Atlanta for use of up to 700 beds at the Atlanta City Detention Center (ACDC) will expire on December 31, 2026.  ACR Partners has been asked to provide comprehensive program management services for a 600-bed modular facility to be constructed on the existing Rice St. jail campus to eliminate the need for long-term use of ACDC.  This request for approval amends the existing contract to include two (2) additional professional services that will occur concurrently with the scope of the original contract as follows:

 

1.                     Programming & Site Feasibility: At the request of Fulton County, ACR Partners will conduct a project kickoff meeting with key stakeholders including DREAM, the Fulton County Sheriff’s Office and the Office of the County Manager. This effort will include reviewing all relevant documentation including facility assessments, population forecasts, and operational data to develop the overall project plan that will result in a new 600-bed modular facility on the existing jail campus. 

 

2.                     Interim Housing Program Management: At the request of Fulton County, ACR Partners will provide program management services for construction of Interim Housing (600-bed modular facility). These services will occur concurrently with phase 2 of the overall Jail Capital Improvement Plan.  The Interim Housing is intended to eliminate outsourcing needs between expiration of the existing lease agreement with the City of Atlanta for use of the Atlanta City Detention Center and the completion of the planned Special Purpose Building.

 

Cost of Additional Services:

 

 

Description of Service

Estimated Project Hours

Cost

1

Program and Site Feasibility

5,344

$1,219,040.00

2

Interim Housing Management

8,614

$1,878,241.44

 

Total

14,174

$3,097,281.44

 

Year 2 Contract amount                                                                                                          $2,032,953.58

Cost of Additional Services                                                                                                         $3,097,281.44

Total Spending Authority for Year 2                                                               $5,130,235.02

 

Community Impact: The successful completion of this Jail Capital Improvement Program (“CIP”) will preserve the life of the existing jail facilities and provide a safer and more reliable environment for both staff and detainees.

 

Department Recommendation: The Department of Real Estate and Asset Management recommends approval.

 

Project Implications: This amendment is necessary to assist DREAM in facilitating the delivery of a modular housing facility necessary to provide adequate housing resources throughout the jail capital improvement program.

 

Community Issues/Concerns: None that the Department is aware.

 

Department Issues/Concerns: If this amendment is not approved, there will be delay in the delivery of jail housing resources.

 

Contract Modification

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount (Year 1)

24-0798

11/20/24

$1,740,749.38

Amendment No. 1 (Year 2)

 

 

$5,130,235.02

Total Revised Amount

 

 

$6,870,984.40

 

 

Contract & Compliance Information

Contract Value:                                          $5,130,235.02

Prime Vendor:                     ACR Partners (JV - 40%/35%/25%)

AECOM - $2,052,094.01 or 40.00%  - Non Minority

Comprehensive Program Service (CPS) - $1,795,582.26 or 35.00% - White Female Business Enterprise

H.J. Russell - $1,282,558.76 or 25.00% - African American Male

 

Location:                                                               Atlanta, GA                                                               

County:                                                               Fulton County

Prime Value:                                          $5,130,235.02 or 100.00%

 

Total Contract Value:                     $5,130,235.02 or 100.00%

Total Certified Value:                     $3,078,141.01  or 60.00%

 

Exhibits Attached

Exhibit 1:  Amendment No. 1 to Form of Contract

Exhibit 2:  Cost Proposal

Exhibit 3:  Performance Evaluation

 

Contact Information
title

Joseph N. Davis, Director, Department of Real Estate and Asset Management, (404) 612-3772

 

Contract Attached
title

Yes


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$1,740,749.38

Previous Adjustments:

$0.00

This Request:

$5,130,235.02

TOTAL:

$6,870,984.40


Fiscal Impact / Funding Source

Funding Line 1:

503-520-5200-1190: TAD Facility Capital Fund, Real Estate and Asset Management, Project Management - $5,130,235.02

 

Key Contract Terms

Start Date: Upon BOC Approval

End Date: 12/11/2029

Cost Adjustment: $3,097,281.44

Renewal/Extension Terms: One, two year renewal option

 

title

 

body

Overall Contractor Performance Rating: 88

 

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

1/7/2025

4/6/2025