Title: Request approval of a recommended proposal - Public Works, 23RFP139070K-JAJ, Progressive Design/Build Services for Campbellton Pump Station and Force Main in an amount not to exceed $1,918,000.00 with Sol Construction, LLC to deliver an 80% design with a guaranteed maximum price (GMP) associated with the design and construction of the Campbellton Pump Station and Force Main effective upon issuance of the Notice to Proceed for 180 consecutive days. (APPROVED)
Attachments: 1. Exhibit 1: Evaluation EC Letter for Campbellton Road Project Final Version, 2. Exhibit 2: CPR-Sol Construction

DEPARTMENT
Public Works

REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title

Request approval of a recommended proposal - Public Works, 23RFP139070K-JAJ, Progressive Design/Build Services for Campbellton Pump Station and Force Main in an amount not to exceed $1,918,000.00 with Sol Construction, LLC to deliver an 80% design with a guaranteed maximum price (GMP) associated with the design and construction of the Campbellton Pump Station and Force Main effective upon issuance of the Notice to Proceed for 180 consecutive days. (APPROVED)
body

REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with the State of Georgia O.C.G.A ? 36-91-1 et seq., Georgia Local Government Public Works Construction Law, all competitive sealed bids costing $100,000 or more for public works construction projects shall be forwarded to the Board of Commissioners for approval.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Health and Human Services

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
Yes

SUMMARY & BACKGROUND: The South Fulton Capacity Study, presented to the BOC as Item No. 21-0143 on 2/17/2021, detailed the sanitary sewer services throughout the South Fulton County service area needed to maintain the expected levels of service and accommodate the anticipated developmental needs. The Campbellton Pump Station and its associated force main was quantified and located to best prepare the County for where developmental growth would occur and the impact that growth would have on the County's existing facilities.

Scope of Work: This project encompasses the completion of the existing Campbellton PS design and providing the County with a guaranteed maximum price (GMP) to complete construction of the Campbellton Pump Station and its associate...