Title: Request approval of a recommended proposal - Public Works, 23RFP052223K-JA, Design-Build Services for Camp Creek Water Reclamation Facility in the amount of $9,725,000.00 with Reeves Young/GMC, JV to provide design-build services for the Camp Creek WRF North Plant. Effective upon issuance of the Notice to Proceed for seven hundred (700) consecutive/calendar days. (APPROVED)
Attachments: 1. Exhibit 1: Evaluation Committee Recommendation Letter, 2. Exhibit 2: Reeves Young-GMC 2022-23 CPR, 3. Exhibit 3: Single_Bid_Analysis_Form+ 23RFP052223K-JA FSW, 4. 2023-0825

DEPARTMENT
Public Works

REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title

Request approval of a recommended proposal - Public Works, 23RFP052223K-JA, Design-Build Services for Camp Creek Water Reclamation Facility in the amount of $9,725,000.00 with Reeves Young/GMC, JV to provide design-build services for the Camp Creek WRF North Plant. Effective upon issuance of the Notice to Proceed for seven hundred (700) consecutive/calendar days. (APPROVED)
body

REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute, or code requirement)
In accordance with the State of Georgia O.C.G.A. ? 36-91 Georgia Local Government Public Works Construction Law, all competitive sealed proposals (RFPs) for public works construction projects (CM at Risk, Construction PM, D/B Projects) costing $100,000.00 or more shall be forwarded to the Board of Commissioners for approval.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Health and Human Services

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
Yes

SUMMARY & BACKGROUND: The Camp Creek Water Reclamation Facility is responsible for the safe treatment of sanitary wastewater flows in South Fulton County. The current facility is permitted to treat up to 24MGD (million gallons per day) of sanitary wastewater.

Scope of Work: This is an immediate needs project focusing on the primary and secondary clarifiers of the Camp Creek WRF North Plant and its associated jet blower system. The North Plant of Camp Creek has three (3) primary and three (3) secondary clarifiers that have reached the end of their useful design lives. This project will replace the mechanical components of those facilities and repair any concrete deficiencies that are noted in the drained tankage. Camp Creek is a biological plant that depends on the performance of micr...