File #: 25-0885    Version: 1 Name:
Type: CM Action Item - Health and Human Services Status: Passed
File created: 10/1/2025 In control: Board of Commissioners
On agenda: 11/19/2025 Final action: 11/19/2025
Title: Request approval to increase spending authority - Department of Public Works, 23ITB139005A-JWT, Standby Utility Pavement Patching & Paving Services in an amount not to exceed $200,000.00 with the K&E Group USA, LLC (Atlanta, GA) to provide standby utility pavement patching and paving services. Effective upon BOC approval through December 31, 2025. (APPROVED)
Attachments: 1. Exhibit 1: Contract Amendment Form, 2. Exhibit 2: Contractor Performance Report

DEPARTMENT
Public Works

REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title

Request approval to increase spending authority - Department of Public Works, 23ITB139005A-JWT, Standby Utility Pavement Patching & Paving Services in an amount not to exceed $200,000.00 with the K&E Group USA, LLC (Atlanta, GA) to provide standby utility pavement patching and paving services. Effective upon BOC approval through December 31, 2025. (APPROVED)
body

REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Health and Human Services

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
Yes

SUMMARY & BACKGROUND: This request is for an increase in spending authority for K&E Group USA, LLC (Atlanta, GA) to provide standby utility pavement patching and paving services.
This is a unit-based contract, and the unit prices are subject to adjustment, either an increase or a decrease. If the quantities for any work items increase, the Bidder agrees to perform the additional work at the unit prices originally quoted.
The requested increase in spending is due to the following factors:

1. An increased number of projects that required paving were completed this summer.
2. The sizes of the patches are much larger than initially planned because the cities are requiring full lane patches beginning and ending 100 feet before the utility cut. For example, a relatively small 6x6 utility cut, the cities are requiring t...

Click here for full text