Request approval for use of Beltline TAD Funds - Fulton County Library System, Library Capital Improvement Program Phase II (FCLS-CIP), Design/Build services in the amount of $998,000.00, to provide continued Program Management and Construction Services for an additional twelve (12) month period to complete project construction and project adds for Phase II library renovation and expansion projects. Effective dates: January 1, 2023, through December 31, 2023. (APPROVED)
body
REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with Resolution No. 16-1011, dated November 2, 2016 which provides that the County Manager and the Finance Department are directed to allocate and utilize BeltLine PILOT payments for capital improvements in accordance with the Library Master Plan.
STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Arts and Libraries
COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?
IS THIS A PURCHASING ITEM?
No
SUMMARY & BACKGROUND THE Fulton County Library System request approval to use Beltline TAD Funds to provide Program Management Services and Construction Services for the completion of Phase II library projects.
Scope of Work: The Fulton County Library System request approval to use Beltline TAD Funds in the amount of $998,000.00 for continued Program Management Services and Construction Services of remaining Phase II library projects. Program Management Services will extend from January 1, 2023, through December 31, 2023.
Beltline TAD Funding Available:
* $12,380,116.30 Funds available prior to this request
* $ 998,000.00 Current TAD Fund request
* $11,382,116.30 TAD Funds remaining for use
Community Impact: This request involves construction on libraries...