Request for the rescission of the approval of a public art contract with David Moore and Adam Deck related to the Rogers Bridge Public Art Project in Johns Creek pursuant to Agenda Item 22-0964 on December 21, 2022. (APPROVED)
body
Requirement for Board Action (Cite specific Board policy, statute or code requirement)
In accordance with O.C.G.A § 36-10-1, requests for approval of contractual agreements shall be forwarded to the Board of Commissioners for approval.
Strategic Priority Area related to this item (If yes, note strategic priority area below)
Arts and Libraries
Commission Districts Affected
All Districts ☒
District 1 ☐
District 2 ☐
District 3 ☐
District 4 ☐
District 5 ☐
District 6 ☐
Is this a purchasing item?
No
Summary & Background
Scope of Work: The Department of Arts & Culture proposes to rescind the award made to David Moore and Adam Deck on December 21, 2022 (Agenda Item 22-0964) to commission original works of art at three locations in Fulton County.
On March 16, David Moore contacted the department to notify us of his resignation from the project. His collaborator, Adam Deck was given the opportunity to apply as a solo artist on March 28, however, he did not submit a portfolio for consideration. Therefore, the Department recommends rescinding the award and appointing an alternative artist.
The contract with the selected artist was never executed and therefore, no funds were expended.
Community Impact: NA
Department Recommendation: Department recommends rescinding the award to David Moore and Adam Deck
Project Implications: The project is unable to move forward until the award is rescinded and an alternative artist is appointed.
Community Issues/Concerns: None
Department Issues/Concerns: None
Fiscal Impact / Funding Source
Funding Line 1:
461-181-JCAP-1160