DEPARTMENT
Public Works
REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title
Request approval of a recommended proposal - Department of Public Works, RFP 24RFP0808K-DB; the Progressive Design/Build for Johns Creek Environmental Campus Membrane System Replacement, to provide Progressive Design-Build Services ("PDB Services") for the design and construction of Johns Creek Environmental Campus (JCEC) Expansion and Membrane System Upgrade Project Phase. Effective for 180 consecutive days upon issuance of the Notice to Proceed.
body
REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with the State of Georgia O.C.G.A. ? 36-91-1, et seq., Georgia Local Government Public Works Construction Law, all competitive sealed bids costing $100,000 or more for public works construction projects shall be forwarded to the Board of Commissioners for approval.
STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Health and Human Services
COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?
IS THIS A PURCHASING ITEM?
Yes
SUMMARY & BACKGROUND: JCEC is located at 8100 Holcomb Bridge Rd in Roswell and operates under NPDES Permit GA0038831. The plant treats wastewater from residential, commercial, and industrial users in North Fulton County, primarily east of GA 400. The County's intention is to proactively upgrade and replace the membrane system, which is original to the 2009 plant construction.
Since its startup in 2009, the plant has been permitted to discharge a combined total of 15 MGD monthly average flow to the Chattahoochee River and the Johns Creek reuse system. Additionally, the County holds 5 MGD of treatment capacity through the former, and now closed, Cauley Creek permit. The Department of Public Works (DPW) desires to add the 5 MGD capacity to JCEC's existing 15 MGD...
Click here for full text