File #: 24-0061    Version: 1 Name:
Type: CM Action Item - Open & Responsible Government Status: Passed
File created: 12/21/2023 In control: Board of Commissioners
On agenda: 1/24/2024 Final action: 1/24/2024
Title: Request approval for use of Beltline TAD Funds - Fulton County Library System, Library Capital Improvement Program Phase II (FCLS-CIP), Design/Build services in the amount of $2,797,780.00, to facilitate completion of additional construction projects for Phase I and Phase II library construction/renovation projects. Effective upon BOC approval. (APPROVED)
Attachments: 1. Exhibit 1- Library Spend Down Plan

DEPARTMENT
Library

REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title
Request approval for use of Beltline TAD Funds - Fulton County Library System, Library Capital Improvement Program Phase II (FCLS-CIP), Design/Build services in the amount of $2,797,780.00, to facilitate completion of additional construction projects for Phase I and Phase II library construction/renovation projects. Effective upon BOC approval. (APPROVED)
body
REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with Resolution No. 16-1011, dated November 2, 2016 which provides that the County Manager and the Finance Department are directed to allocate and utilize Beltline PILOT payments for capital improvements in accordance with the Library Master Plan.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Arts and Libraries

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
No

SUMMARY & BACKGROUND: Approval to use Beltline TAD Funds to allow the completion of additional projects throughout library facilities that are part of the Library Capital Improvement Program (CIP) Phase I and Phase II construction and renovation projects.

Scope of Work: The Fulton County Library System request approval to use Beltline TAD Funds in the amount of $2,797,780.00 for the completion of additional projects on numerous libraries that are part of the Library CIP Phase I and Phase II.

Beltline TAD Funding Available:

* $12,493,950.00 Funds available prior to this request
* $2,797,780.00 Current TAD Fund request
* $9,696,170.00 TAD Funds remaining for use

Community Impact: This request involves construction on libraries located in communities throughout the County. The successful completion of these library construction projects will impact communities throughout the Cou...

Click here for full text