DEPARTMENT
Public Works
REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title
Request approval of extend an existing contract - Public Works Department, 22ITB136410K-BKJ, Pine Valley Phase 2A Interceptor Sewer Replacement at no additional cost for extension of "time only" with Wade Coots Company, Inc (Austell, GA) to provide all labor, material and equipment to remove and replace approximately 4,062 feet of 30" to 48" RCP gravity sewer pipe with 54" HOBAS fiberglass pipe and epoxy coated precast concrete manholes. Effective upon Boc approval through March 31, 2025. (APPROVED)
body
REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.
STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Health and Human Services
COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?
IS THIS A PURCHASING ITEM?
Yes
SUMMARY & BACKGROUND: The Department of Public Works requests approval to extend "time only" with Wade Coots Company, Inc. (Austell, GA) to provide construction Management services for the Pine Valley Sewer Replacement Phase 2A project.
Scope of Work: The Pine Valley Sewer Replacement Phase 2A project involves supplying all necessary labor, equipment, and materials for installing 4,062 linear feet of 54-inch Hobas sanitary sewer pipe.
The original contract approved by the Board of Commissioners on May 3, 2023 (Agenda #23-0313) had a completion date of July 16, 2024. However, design modifications were required as a result of unforeseen site conditions, which included rock...
Click here for full text