File #: 22-0662    Version: 1 Name:
Type: Consent - Health and Human Services Status: Agenda Ready
File created: 8/5/2022 In control: Board of Commissioners
On agenda: 9/21/2022 Final action:
Title: Request approval of a change order less than 10% - Public Works Department, 21ITB129828K-JAJ, Camp Creek WRF UV Replacement in the amount of $113,911.00 with Archer Western Construction, LLC (Atlanta, GA) to provide construction services related to the Camp Creek WRF UV replacement. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
Attachments: 1. Exhibit 1: Change Order Agreement, 2. Exhibit 2: Contractor's Report 2nd Quarter 2022, 3. Exhibit 3: Cost Breakdown PCI 006 - UV System Electrical and Cable, 4. 2022-0662
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT
Public Works

REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title

Request approval of a change order less than 10% - Public Works Department, 21ITB129828K-JAJ, Camp Creek WRF UV Replacement in the amount of $113,911.00 with Archer Western Construction, LLC (Atlanta, GA) to provide construction services related to the Camp Creek WRF UV replacement. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
body

REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Health and Human Services

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
Yes

SUMMARY & BACKGROUND: This project involves replacement of the ultraviolet (UV) system. The UV system is the main component of the final treatment process at the Camp Creek Water Reclamation Facility (WRF) before the treated water is returned to the Chattahoochee River through Camp Creek. This stage of treatment is responsible for eliminating viruses and bacteria that may be harmful to the people and the environment. The current UV system has reached the end of its useful design life.

Scope of Work: The manufacturer of the chosen UV system provided additional information regarding the sizing of the UV system necessary for Camp Creek WRF. This change order represents the costs associated with ensuring that the UV system is properly sized. The current change order reflects credits from the UV system manufacturer...

Click here for full text