REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title
Presentation and discussion of the South Fulton Wastewater Capacity Study.
body
REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
None - This item is presented for information purposes only.
STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Health and Human Services
SUMMARY & BACKGROUND (First sentence includes Agency recommendation. Provide an executive summary of the action that gives an overview of the relevant details for the item.)
Scope of Work:
In the fall of 2019, Public Works, with assistance from the consulting firm Gresham Smith, undertook a 40-year study to assess the current wastewater conveyance and treatment infrastructure in the area served by Fulton County Public Works in the South Fulton County area. The study include participation of all South Fulton County cities including Chattahoochee hills, College Park, East Point, Fairburn, Palmetto, South Fulton, and Union City.
Public Works and Gresham Smith staff met with each city to review their current development and comprehensive plans to better under the types and densities of new and redevelopment each city is anticipating over the next forty years. These growth projections were used to develop sanitary sewer needs for the 2020 - 2029, 2030-2039, 2040-2049, and 2050-2059 planning years.
The study included an evaluation of the existing gravity sanitary sewers, force main sewers, and pump stations currently in service throughout the South Fulton service area. Additionally, the study identified areas in the South Fulton area currently not being served by sewer and identified were new pump stations, force mains and gravity sewers should be extended to accommodate the planned growth.
The findings of the study included the identification of 122,500 linear feet of new gravity sewer pipes, 34,600 linear feet of upsizin...
Click here for full text