Skip to main content
File #: 25-0458    Version: 1 Name:
Type: Consent - Health and Human Services Status: Agenda Ready
File created: 3/4/2025 In control: Board of Commissioners
On agenda: 6/18/2025 Final action:
Title: Request approval of an Intergovernmental Agreement (IGA) between Fulton County, Georgia and Union City, Georgia for sanitary sewer services. This agreement establishes how the 3MG reserve capacity for Union City, at the Camp Creek WRF, will be managed for a period of 15 years with a potential 5-year extension. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
Attachments: 1. Exhibit A - Sewer Service Area, 2. Exhibit B - Flow Monitor Location, 3. Exhibit C - Interceptor Sewer Location, 4. Union City Wastewater IGA 2025
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT
Public Works

REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title
Request approval of an Intergovernmental Agreement (IGA) between Fulton County, Georgia and Union City, Georgia for sanitary sewer services. This agreement establishes how the 3MG reserve capacity for Union City, at the Camp Creek WRF, will be managed for a period of 15 years with a potential 5-year extension. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
body

REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
GA CONST Art. 9, Sec. 3, Para. I provides that the County may contract for any period not exceeding 50 years with any other public agency, public corporation, or public authority for joint services, for the provision of services, or for the joint or separate use of facilities or equipment; but such contracts must deal with activities, services, or facilities that the contracting parties are authorized by law to undertake or provide. O.C.G.A. Sec. 36-10-1 requires that all official contracts entered into by the County governing authority with other persons on behalf of the County shall be in writing and entered on its minutes.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Health and Human Services

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
No

SUMMARY & BACKGROUND (First sentence includes Agency recommendation. Provide an executive summary of the action that gives an overview of the relevant details for the item.)

Scope of Work:
On July 17, 2013 Fulton County and Union City entered into an agreement to allow Fulton County to accept and treat wastewater collected within the sanitary sewer owned Union City. This agreement was set to expire in July 2028. Union City requested a new agreement to clarify the areas o...

Click here for full text