File #: 21-0776    Version: 1 Name:
Type: CM Action Item - Infrastructure and Economic Development Status: Passed
File created: 9/9/2021 In control: Board of Commissioners
On agenda: 10/6/2021 Final action: 10/6/2021
Title: Request approval of a change order greater than 10% - Department of Public Works, 20ITB126597KJAJ, Airfield Lighting & Rehabilitation at Fulton County Executive Airport at Charlie Brown Field in an amount not to exceed $199,816.00 with Precision Approach, LLC (Eatonton, GA), to provide airfield lighting and signage rehabilitation Runways 8/26 & 14/32 and Taxiways Alpha and Bravo. Effective upon BOC approval. (APPROVED)
Attachments: 1. Exhibit 1: Change Order No1 to Form of Contract, 2. Exhibit 2: Contractor Performance Report

 

Department

Public Works

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

Request approval of a change order greater than 10% - Department of Public Works, 20ITB126597KJAJ, Airfield Lighting & Rehabilitation at Fulton County Executive Airport at Charlie Brown Field in an amount not to exceed $199,816.00 with Precision Approach, LLC (Eatonton, GA), to provide airfield lighting and signage rehabilitation Runways 8/26 & 14/32 and Taxiways Alpha and Bravo. Effective upon BOC approval. (APPROVED)

 

body

Requirement for Board Action (Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Infrastructure and Economic Development

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background (First sentence includes Agency recommendation. Provide an executive summary of the action that gives an overview of the relevant details for the item.)

 

Scope of Work: This change order will provide additional electrical upgrades and rehabilitation to the airfield lighting systems on runways 8/26, 14/32, and taxiways Alpha and Bravo. The work will include troubleshooting, repair, and upgrades to runway lights, taxiway lights, wind cones, runway end indicator lights (REILS), and associated regulator vault upgrades. These systems were not included in the initial contact work and were identified by Airport staff during the initial work as also needing to be addressed.

 

Community Impact: The work will be completed on current Airport property, so no direct impact to the community is expected.

 

Department Recommendation: The Department of Public Works recommends approval of change order greater than 10% with Precision Approach, LLC.

 

Project Implications: This project will replace additional deteriorating lighting system components   identified during the rehabilitation project of the runway 8/26 lighting system for Fulton County Executive Airport. If not replaced, the lighting system will eventually fail and the airport would then be limited to daytime, clear weather, operations only.

 

Community Issues/Concerns: None have been expressed nor are expected due to the work being done on the airfield.

Department Issues/Concerns: No issues or concerns have been raised by Public Works Staff.

 

Contract Modification:

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

20-0807

11/18/2020

$937,014.00

Change Order #1

 

 

$199,816.00

Total Revised Amount

 

 

$1,136,830.00

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Total Contract Value:                     $199,816.00

 

Contract Value:                                          $ 199,816.00

Prime Vendor:                     Precision Approach, LLC

Prime Status:                     Non-Minority

Location:                                                               Eatonton, GA

County:                                                               Putman County

Prime Value:                                          $199,816.00 or 100.00%

 

Total Contract Value:                     $199,816.00 or 100.00%

Total M/FBE Value:                      -0- 

 

Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)

Exhibit 1: Change Order No. 1 to Form of Contract

Exhibit 2: Contractor Performance Report

 

Contact Information (Type Name, Title, Agency and Phone)
title

Tim Beggerly, Airport Manager, Public Works 404-613-4203

 

Contract Attached
title

No


Previous Contracts

title

Yes

 

 

 

Total Contract Value

Original Approved Amount:

$   937,014.00

Previous Adjustments:

$              0.00

This Request:

$   199,816.00

TOTAL:

$1,136,830.00


Grant Information Summary

Amount Requested:

.

Cash

Match Required:

.

In-Kind

Start Date:

.

Approval to Award

End Date:

.

Apply & Accept

Match Account $:

.

 

 


Fiscal Impact / Funding Source

Funding Line 1:

509-540-5601-AIR1: Transportation Improvement Plan, Public Works, Runway and Taxiway Repair - $199,816.00

Key Contract Terms

Start Date: Effective upon BOC approval

End Date: Click here to enter a date.

Cost Adjustment: .

Renewal/Extension Terms: .


Overall Contractor Performance Rating: 4.0

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

4/12/2021

6/12/2021