Title: Request approval to renew existing contracts - Department of Public Works, 201TB092320A-FB, Large Water Meter Installation Services in the amount of $750,000.00 with Wade Coots Company, Inc. (Austell, GA), to provide large water meter installation services. This action exercises the first of two renewal options. One renewal option remains. Effective dates: January 1, 2022 through December 31, 2022. (APPROVED)
Attachments: 1. Exhibit 1: Contract Renewal Agreement, 2. Exhibit 2: Contractor Performance Report, 3. Exhibit 3: Contract Renewal Evaluation Form

DEPARTMENT
Public Works

REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title

Request approval to renew existing contracts - Department of Public Works, 201TB092320A-FB, Large Water Meter Installation Services in the amount of $750,000.00 with Wade Coots Company, Inc. (Austell, GA), to provide large water meter installation services. This action exercises the first of two renewal options. One renewal option remains. Effective dates: January 1, 2022 through December 31, 2022. (APPROVED)
body

REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Section 102-394(6), the Purchasing Department shall present all renewal requests to the Board of Commissioners at least 90 days prior to the contract renewal date, 60 days if the contract term is six (6) months or less.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Health and Human Services

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
Yes

SUMMARY & BACKGROUND: The Department of Public Works recommends approval to renew existing contract to provide large water meter installation services.

Scope of Work: The Large Meter installation contract allows for the installation of large water meters (meters greater than 2") on fire service lines and larger water lines servicing new developments. Additionally, this contract allows for the replacement of existing large water meters when necessary.

Community Impact: The metering of large water services properly accounts for water consumption by large consumption users of the water system.

Department Recommendation: The Department request approval to renew existing contract to Wade Coots Company, Inc.

Project Implications: The Large Meter installation contract provides installation of meters on unmetered fire services,...