File #: 21-0875    Version: 1 Name:
Type: CM Action Item - Health and Human Services Status: Passed
File created: 10/4/2021 In control: Board of Commissioners
On agenda: 11/3/2021 Final action: 11/3/2021
Title: Request approval of a recommended proposal - Department of Public Works, RFP#21RFP130845K-BKJ, Progressive Design-Build Services for Atlanta Newnan Road Pump Station and Force Main in the amount of $590,000.00 with Reeves Young /GMC JV, to provide Progressive Design-Building services for the design and construction of the Atlanta Newnan Road Pump Station and associated force main pipeline. Effective upon execution of contract for 180 consecutive days upon issuance of the Notice to Proceed. (APPROVED)
Attachments: 1. Exhibit 1 - Atlanta Newnan Project Recommendation Letter, 2. Exhibit 2 - Contractor Performance Memo Atlanta Newnan Rd PS

DEPARTMENT
Public Works

REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title

Request approval of a recommended proposal - Department of Public Works, RFP#21RFP130845K-BKJ, Progressive Design-Build Services for Atlanta Newnan Road Pump Station and Force Main in the amount of $590,000.00 with Reeves Young /GMC JV, to provide Progressive Design-Building services for the design and construction of the Atlanta Newnan Road Pump Station and associated force main pipeline. Effective upon execution of contract for 180 consecutive days upon issuance of the Notice to Proceed. (APPROVED)
body

REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with the Purchasing Code Sections 102-374, all competitive sealed proposals shall be forwarded to the Board of Commissioners for approval.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Health and Human Services

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
Yes

SUMMARY & BACKGROUND

Scope of Work:
The Atlanta Newnan Road Pump Station and Force Main Project will construct two (2) new pump stations and approximately forty-six thousand linear feet, 8.8 miles, of force main pipeline to serve the areas around the Serenbe and Crossroads developments in Chattahoochee Hills. The new pump stations and force main pipeline will direct untreated wastewater from this section of South Fulton County to the existing Ono Road pump station. From the Ono Road pump station, an existing network of pump stations, force mains, and gravity sanitary sewer lines will carry the wastewater to the Camp Creek water reclamation facility for treatment. One of the pump stations will be located on the same property as the existing Little Bear Creek Water Reclamation Facility in the Crossroads residential subdivision. Th...

Click here for full text