Title: Request approval of a change order less than 10% - Department of Real Estate and Asset Management, 20RFP127341K-DB, Judge Romae T. Powell-Fulton County Juvenile Justice Facility Building Automation System Upgrades, Air Handling Unit Repairs and Chiller Replacements in the amount of $123,073.00 with Trane U.S., Inc. (Atlanta, GA), to modify the existing Scope of Work to provide additional repairs and replacement of primary and secondary chiller pumps discovered during the upgrade renovation project of the BAS Controls, AHU and Chillers at the Fulton County Judge Romae T. Powell Juvenile Justice Center; and, to extend the existing contract for an additional four (4) month period in order to complete the work through October 31, 2022. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
Attachments: 1. a Exhibit 1 Change Order No. 1 to Form of Contract, 2. Exhibit 2 Change Order Proposal, 3. Exhibit 3 Contractor's Performance Report, 4. 2022-0384.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT
Real Estate and Asset Management

REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title

Request approval of a change order less than 10% - Department of Real Estate and Asset Management, 20RFP127341K-DB, Judge Romae T. Powell-Fulton County Juvenile Justice Facility Building Automation System Upgrades, Air Handling Unit Repairs and Chiller Replacements in the amount of $123,073.00 with Trane U.S., Inc. (Atlanta, GA), to modify the existing Scope of Work to provide additional repairs and replacement of primary and secondary chiller pumps discovered during the upgrade renovation project of the BAS Controls, AHU and Chillers at the Fulton County Judge Romae T. Powell Juvenile Justice Center; and, to extend the existing contract for an additional four (4) month period in order to complete the work through October 31, 2022. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
body

REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Open and Responsible Government

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
Yes

SUMMARY & BACKGROUND Request approval of Change Order No. 1 to provide additional repairs and replacement of primary and secondary chiller pumps for the BAS Controls, AHU and Chillers Project at the Fulton County Judge Romae T. Powell Juvenile Justice Center.

Scope of Work: The Contractor will perform the additional services to provide repairs and replacement of prima...