File #: 22-0419    Version: 1 Name:
Type: Consent - Health and Human Services Status: Agenda Ready
File created: 4/21/2022 In control: Board of Commissioners
On agenda: 6/15/2022 Final action:
Title: Request approval of a change order less than 10% - Department of Public Works, 20ITBC125292A-FB, Ductile Iron Pipe, Restraining Gaskets, and Tapping Saddles to increase the unit prices as outlined in the attached pricing sheet, no additional funding required, with Ferguson Waterworks (Norcross, GA), to provide ductile iron pipe, restraining gaskets and tapping saddles. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
Attachments: 1. Exhibit 1: Change Order Agreement, 2. Exhibit 2: Contractor Performance Report, 3. Exhibit 3: Revised Pricing Sheet
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Department

Public Works

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval of a change order less than 10% - Department of Public Works, 20ITBC125292A-FB, Ductile Iron Pipe, Restraining Gaskets, and Tapping Saddles to increase the unit prices as outlined in the attached pricing sheet, no additional funding required, with Ferguson Waterworks (Norcross, GA), to provide ductile iron pipe, restraining gaskets and tapping saddles. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA) 

body

Requirement for Board Action (Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Health and Human Services

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background The Department of Public Works is requesting approval of a change order less than 10%, 20ITBC125292A-FB Ductile Iron Pipe, Restraining Gaskets, and Tapping Saddles to increase the unit prices as outlined in the attached pricing sheet.

 

Scope of Work: The contract with Ferguson Waterworks provides ductile iron pipes, restraining gaskets, and tapping saddles to maintain and repair water infrastructure throughout the North Fulton County water service areas. The renewal of the 2022 contract was approved by the Board of Commissioners on November 17, 2021. However, due to the pandemic which is impacting the supply chain and the availability of materials, Ferguson Waterworks requests an average increase of 25% of the previously approved unit prices.  The new unit prices for the various materials purchased by Public Works under this contract are shown in Exhibit 1.  No additional spending authority is required.

 

Community Impact: Approval of unit price increases will avoid delays in procurement of ductile iron pipe, restraining gaskets, and tapping saddles. Failure to procure and maintain these items in stock can negatively impact the operation of the Water Services Division in maintaining water systems and services.

 

Department Recommendation: The Department of Public Works recommends approval of a change order less than 10% to the contract with Ferguson Waterworks not to exceed the awarded amount of $92,779.16.

 

Project Implications: Increase in unit cost without increasing the awarded contract amount may inhibit the ability to procure ductile iron pipe, restraining gaskets, and tapping saddles for water service installation, repair, and maintenance for the North Fulton water distribution system.

 

Community Issues/Concerns: Public Works staff is not aware of any community issues or concerns.

 

Department Issues/Concerns: The Department of Public Works does not have any issues or concerns with the proposed price increase.

 

Contract Modification

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

20-0548

8/5/2020

$105,126.30

1st Renewal

20-0923

12/16/2020

$105,126.30

2nd Renewal

21-0894

11/17/2021

$92,779.16

Change Order No 1

 

 

$.00

Total Revised Amount

 

 

$303,031.76

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Total Contract Value:                      $0

Prime Vendor:                                      Ferguson Waterworks
Prime Status:                 
                     Non-Minority
Location:                                              Braselton, GA
County:                                                Barrow County
Prime Value:                                                          $0 or 100.00%

Total Contract Value:                          $0 or 100.00%
Total M/FBE Value:
                     -0-

 

Exhibits Attached (Provide copies of originals, number exhibits consecutively, and label all exhibits in the upper right corner.)

Exhibit 1: Change Order Agreement No. 1

Exhibit 2: Contractor Performance Report

Exhibit 3: Revised Pricing Sheet

 

Contact Information (Type Name, Title, Agency and Phone)
title

Nick Ammons, Deputy Director, Public Works, 404-612-7530

 

 

Contract Attached
title

Yes


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$105,126.30

Previous Adjustments:

$197,905.46

This Request:

$           0.00

TOTAL:

$303,031.76


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

203-540-5453-1450: Water & Sewer R & E, Public Works, Maintenance Supplies - $0.00

Key Contract Terms

Start Date: 1/1/2022

End Date: 12/31/2022

Cost Adjustment:

Renewal/Extension Terms: none


Overall Contractor Performance Rating: 3.0

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

3/5/2021

6/22/2021