File #: 22-0539    Version: 1 Name:
Type: CM Action Item - Health and Human Services Status: Passed
File created: 5/25/2022 In control: Board of Commissioners
On agenda: 8/3/2022 Final action: 8/3/2022
Title: Request approval to increase spending authority - Department of Public Works, SWC 99999-SPDS20190913B Equipment Rental - Wastewater System Services in an amount not to exceed $1,850,000.00 with Sunbelt Rentals (Fort Mill, SC) to provide rental by-pass pumping equipment - wastewater system services. Effective upon BOC approval. (APPROVED)
Attachments: 1. Exhibit 1: CPR - Sunbelt Jan-March 2022 signed copy

 

Department

Public Works

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval to increase spending authority - Department of Public Works, SWC 99999-SPDS20190913B Equipment Rental - Wastewater System Services in an amount not to exceed $1,850,000.00 with Sunbelt Rentals (Fort Mill, SC) to provide rental by-pass pumping equipment - wastewater system services. Effective upon BOC approval. (APPROVED)

body


Requirement for Board Action
(Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Health and Human Services

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Scope of Work: To provide specialty contracting work that involves temporary generators, bypass chopper pumps, and all other requirements to successfully bypass sanitary sewer facilities for construction rehabilitation.

Community Impact: This authorization is being requested due to unforeseen major delays in the delivery of equipment, a consequence of global supply chain problems, during the emergency repair of the Camp Creek Wastewater Treatment Plant influent pump station. This delay resulted in longer bypass pumping services reducing the amount of money in the original contract available for other bypass needs.   The reduction in funds will impede our ability to provide emergency bypass pumping during our response to sanitary sewer spills. The existing contract expires in August 2022. 

 

Department Recommendation: The Public Works Department recommends approval of this item for additional spending authority. 

Project Implications: This item will allow the department to avoid assigning these services to current standby contractors where there are significant price escalations. This item will allow the Department to avoid assigning these services to current standby contractors where there are significant price escalations. If the increase is not approved, the delay will prevent us from responding in the most responsible manner to emergency conditions. That has the potential to result in more spills, public health concerns, environmental damage, and higher fines from the Environmental Protection Agency (EPD).    

 

Community Issues/Concerns: This action provides the Public Works Department with another tool ensuring a quick and efficient response to situations where failed facilities need to be repaired or replaced.

 

Department Issues/Concerns: The Public Works Department has no concerns related to this item.

 

Contract Modification

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

21-0667

09/01/2021

$2,000,000.00

Increase Spending Authority

 

 

$1,850,000.00

Total Revised Amount

 

 

$3,850,000.00

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Click or tap here to enter text.

 

Exhibits Attached

Exhibit 1: Contract Performance Report

Contact Information (Type Name, Title, Agency and Phone)
title

David E. Clark, Director Public Works, X-22804

 

Contract Attached
title

No


Previous Contracts

title

No

 

Total Contract Value

Original Approved Amount:

 

Previous Adjustments:

 

This Request:

 

TOTAL:

 


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

203-540-5400-S057, Water & Sewer R&E, Public Works, Wastewater Control Sysm Imprvt. $1,850,000.00

 

Key Contract Terms

Start Date: 9/1/2021

End Date: 9/30/2022

Cost Adjustment

Renewal/Extension Terms


Overall Contractor Performance Rating:

Would you select/recommend this vendor again?

Choose an item.

 

Report Period Start:

Report Period End:

1/1/2022

3/31/2022