File #: 22-0642    Version: 1 Name:
Type: CM Action Item - Health and Human Services Status: Passed
File created: 7/12/2022 In control: Board of Commissioners
On agenda: 9/7/2022 Final action: 9/7/2022
Title: Request approval to rescind contract change order - Public Works, 17RFP031617K-DJ Progressive Design/Build Services for Big Creek Water Reclamation Facility (WRF) Expansion Project Phase 2B in the amount of $201,545.00 with Archer Western-Brown and Caldwell Joint Venture (Atlanta, GA) to cover the impact of tariffs for material and equipment and to extend the contract term by eleven (11) additional days due to inclement weather. Effective upon BOC approval. (APPROVED)
Attachments: 1. Exhibit 1: BOC Item #22-0346, 2. Exhibit 2: Interoffice Memorandum Big Creek CO#1

DEPARTMENT
Public Works

REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title

Request approval to rescind contract change order - Public Works, 17RFP031617K-DJ Progressive Design/Build Services for Big Creek Water Reclamation Facility (WRF) Expansion Project Phase 2B in the amount of $201,545.00 with Archer Western-Brown and Caldwell Joint Venture (Atlanta, GA) to cover the impact of tariffs for material and equipment and to extend the contract term by eleven (11) additional days due to inclement weather. Effective upon BOC approval. (APPROVED)
body

REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Sections 102-421, when a contract requires termination or rescission of the award, it shall be forwarded to the Board of Commissioners for approval.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Health and Human Services

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
Yes

SUMMARY & BACKGROUND: The Public Works Department is seeking approval to rescind award of change order #1 which was approved under item #22-0346 at the 5/18/2022 BOC recess meeting. After the approval of the item, it was recognized by the Public Works Department and the JV Consultant that the substantial completion date and corresponding cost in the change order was incorrect. Therefore, a new change order will be developed and forwarded to the BOC with the correct revised substantial completion date and costs.

Community Impact: No impact to the community has been noted.

Department Recommendation: The Public Works Department recommends approval of this item.

Project Implications: The Public Works Department needs to clarify the conditions of the contract. However, the previous approved change order was not correct and needs to be ...

Click here for full text