File #: 22-0861    Version: 1 Name:
Type: CM Action Item - Health and Human Services Status: Passed
File created: 9/28/2022 In control: Board of Commissioners
On agenda: 11/16/2022 Final action: 11/16/2022
Title: Request approval to renew an existing contract - Department of Public Works, 21ITBC000023A-CJC, Water Meter Vaults, in an amount not to exceed $200,000.00 with Bartow Precast, Inc. (Cartersville, GA) to provide water meter vaults. This action exercises the first of two renewal options. One renewal option remains. Effective dates: January 1, 2023, through December 31, 2023. (APPROVED)
Attachments: 1. Exhibit 1: Contract Renewal Agreement Form, 2. Exhibit 2: Contractor Performance Report, 3. Exhibit 3: Contract Renewal Evaluation, 4. Exhibit 4: Pricing Sheet

Department

Public Works

 

Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)

title

 

Request approval to renew an existing contract - Department of Public Works, 21ITBC000023A-CJC, Water Meter Vaults, in an amount not to exceed $200,000.00 with Bartow Precast, Inc. (Cartersville, GA) to provide water meter vaults. This action exercises the first of two renewal options. One renewal option remains. Effective dates: January 1, 2023, through December 31, 2023.  (APPROVED)

body


Requirement for Board Action
(Cite specific Board policy, statute or code requirement)

In accordance with Purchasing Code Section 102-394(6), the Purchasing Department shall present all renewal requests to the Board of Commissioners at least 90 days prior to the contract renewal date, 60 days if the contract term is six (6) months or less.

 

Strategic Priority Area related to this item (If yes, note strategic priority area below)

Health and Human Services

 

Commission Districts Affected

All Districts                     

District 1                     

District 2                     

District 3                     

District 4                     

District 5                     

District 6                     


Is this a purchasing item?

Yes

 

Summary & Background: Department of Public Works recommends approval to renew the existing contract with Bartow Precast, Inc. to provide water meter vaults.

Scope of Work: Provide water meter vaults for the Water Distribution System throughout North Fulton County of the Chattahoochee River. The water meter vaults are used for installation of new water service and the replacement of small and medium size water meters.

 

Community Impact: Without a readily available supply of water vaults, the installation of new water services will not be possible. Maintenance of the water system will be impacted.

 

Department Recommendation: The Department of Public Works recommends approval to renew the existing contract with Bartow Precast, Inc. with one renewal option remaining.

 

Project Implications: Maintaining the Water Distribution System and providing new services will be affected. 

 

Community Issues/Concerns: Public Works is not aware of any Community Issues or concerns

 

Department Issues/Concerns: If not funded, the Department is concerned it will restrict our ability to properly maintain the Water Distribution System and provide new service installations.

 

Contract Modification

 

Current Contract History

BOC Item

Date

Dollar Amount

Original Award Amount

21-0978

12/1/2021

$200,000.00

1st Renewal

 

 

$200,000.00

Total Revised Amount

 

 

$400,000.00

Contract & Compliance Information (Provide Contractor and Subcontractor details.)

Contract Value:                                           $200,000.00

 

Prime Vendor:                                           Bartow Precast, Inc.

Prime Status:                                          Non-Minority

Location:                                                               Cartersville, GA

County:                                                                Bartow County                                          

Prime Value:                                           $200,000.00                     or 100.00%                      

 

Total Contract Value:                      $200,000.00 or 100.00%

Total M/FBE Value:                      -0-

 

Exhibits Attached

Exhibit 1: Contract Renewal Agreement

Exhibit 2: Contractor Performance Report

Exhibit 3: Contract Renewal Evaluation Form

Exhibit 4: Pricing Sheet

 

Contact Information (Type Name, Title, Agency and Phone)
title

Roy Barnes, Deputy Director, Public Works, 404-612-6317

Contract Attached
title

No


Previous Contracts

title

Yes

 

Total Contract Value

Original Approved Amount:

$200,000.00

Previous Adjustments:

$0.00

This Request:

$200,000.00

TOTAL:

$400,000.00


Grant Information Summary

Amount Requested:

 

Cash

Match Required:

 

In-Kind

Start Date:

 

Approval to Award

End Date:

 

Apply & Accept

Match Account $:

 

 

 


Fiscal Impact / Funding Source

Funding Line 1:

203-540-5453-1450: Water & Sewer R & E, Public Works, Maintenance Supplies - $200,000.00

Key Contract Terms

Start Date: 1/1/2023

End Date: 12/31/2023

Cost Adjustment:

Renewal/Extension Terms: One renewal option remains


Overall Contractor Performance Rating: 3.0

Would you select/recommend this vendor again?

Yes

 

Report Period Start:

Report Period End:

7/1/2022

9/30/2022