File #: 23-0075    Version: 1 Name:
Type: Consent - Health and Human Services Status: Agenda Ready
File created: 11/1/2022 In control: Board of Commissioners
On agenda: 2/1/2023 Final action:
Title: Request approval of a change order less than 10% - Public Works, 17RFP031617K-DJ Progressive Design/Build Services for Big Creek Water Reclamation Facility (WRF) Expansion Project Phase 2B in an amount not to exceed $339,444.13 with Archer Western-Brown and Caldwell Joint Venture (JV) (Atlanta, GA) to cover costs associated with eight (8) inclement weather days and additional material (electrical wiring) to connect the new facility to the Georgia Power Substation. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
Attachments: 1. Exhibit #1: CHANGE ORDER AGREEMENT, 2. Exhibit #2-CPR - Archer Western JV, 3. 2023-0075
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT
Public Works

REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title

Request approval of a change order less than 10% - Public Works, 17RFP031617K-DJ Progressive Design/Build Services for Big Creek Water Reclamation Facility (WRF) Expansion Project Phase 2B in an amount not to exceed $339,444.13 with Archer Western-Brown and Caldwell Joint Venture (JV) (Atlanta, GA) to cover costs associated with eight (8) inclement weather days and additional material (electrical wiring) to connect the new facility to the Georgia Power Substation. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
body

REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract, shall be forwarded to the Board of Commissioners for approval.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Health and Human Services

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
Yes

Scope of Work: This request for a change order addresses two immediate elements:
(1) incurred overhead costs associated with eight (8) inclement weather days during the 2022 project year, and (2) additional labor/material costs to connect to the new switch gear and generators within the Georgia Power substation.

The existing authorized contract defines an inclement weather day and stipulates how the owner's directed contingency is utilized to compensate the JV regarding overhead costs. The JV provided supporting documents exhibiting total overhead costs during the eight (8) inclement weather days at $158,...

Click here for full text