File #: 23-0228    Version: 1 Name:
Type: Consent - Health and Human Services Status: Agenda Ready
File created: 2/15/2023 In control: Board of Commissioners
On agenda: 4/12/2023 Final action:
Title: Request approval of a change order less than 10% - Department of Public Works, 20ITB126798K-JAJ, ARFF, Phase II, in an amount not to exceed $174,570.36 with Trident Construction Group (Atlanta, GA) to provide for additional rock removal, additional stairway lighting, millwork changes, and fire line additions at the Aircraft Rescue Firefighting Facility at the Fulton County Executive Airport. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
Attachments: 1. Exhibit 1 :Change Order 3, 2. Exhibit 2: Scope of Work, 3. Exhibit 3 : Contractor Performance Report, 4. 2023-0228
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT
Public Works

REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title

Request approval of a change order less than 10% - Department of Public Works, 20ITB126798K-JAJ, ARFF, Phase II, in an amount not to exceed $174,570.36 with Trident Construction Group (Atlanta, GA) to provide for additional rock removal, additional stairway lighting, millwork changes, and fire line additions at the Aircraft Rescue Firefighting Facility at the Fulton County Executive Airport. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
body

REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract are necessary for contract completion, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the BOC for approval.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Infrastructure and Economic Development

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
Yes

SUMMARY & BACKGROUND: On August 18, 2021, the BOC approved a construction award to Trident Construction Group for the renovation of the Aircraft Rescue Firefighting Facility (ARFF) in an amount not to exceed $2,486,000.00.

On April 13, 2022, the Fulton County BOC approved a change order less than 10% (Net $0.00) with Trident Construction Group to amend the Mechanical Specifications and extend the contract duration by 60 days.

On September 7, 2022, the Fulton County BOC approved a change order less than 10% with Trident Construction Group in an amount not to exceed $101,717.58, including owner's contingency, for additional plumbing, drainage, footings, and slab fill and to amend the corresponding contract specifications and ...

Click here for full text