File #: 24-0271    Version: 1 Name:
Type: CM Action Item - Open & Responsible Government Status: Passed
File created: 3/20/2024 In control: Board of Commissioners
On agenda: 4/17/2024 Final action: 4/17/2024
Title: Request approval of the lowest responsible bidder - Department of Real Estate and Asset Management, 23ITB122123K-DB, Demolition Services for the Super Inn Hotel and the Executive Inn Hotel in an amount not to exceed $1,071,000.00 with Complete Demolition Services, LLC (Carrollton, GA) to provide demolition services for the Super Inn Hotel and the Executive Inn Hotel. Effective upon issuance of Notice to Proceed for a period of 160 calendar days. (APPROVED)
Attachments: 1. Exhibit 1 - Bid Tabulation Sheet, 2. Exhibit 2 Contractor's Performance Report - Completre Demolition Services

DEPARTMENT
Real Estate and Asset Management

REQUESTED ACTION
title

Request approval of the lowest responsible bidder - Department of Real Estate and Asset Management, 23ITB122123K-DB, Demolition Services for the Super Inn Hotel and the Executive Inn Hotel in an amount not to exceed $1,071,000.00 with Complete Demolition Services, LLC (Carrollton, GA) to provide demolition services for the Super Inn Hotel and the Executive Inn Hotel. Effective upon issuance of Notice to Proceed for a period of 160 calendar days. (APPROVED)
body

REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with the State of Georgia O.C.G.A. ?36-91 Georgia Local Government Public Works Construction Law, all competitive sealed bids costing $100,000.00 or more for public works construction projects shall be forwarded to the Board of Commissioners for approval.

STRATEGIC PRIORITY AREA RELATED TO THIS ITEM
Open and Responsible Government

COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?

IS THIS A PURCHASING ITEM?
Yes

SUMMARY & BACKGROUND: To provide complete demolition of all buildings and foundations and the removal and dumping of all construction demolition debris for the Super Inn Hotel located at 301 Fulton Industrial Circle, SW, and the adjacent Executive Inn Hotel located at 305 Fulton Industrial Circle, SW, both in Atlanta, Georgia

Scope of Work: The demolition contractor will furnish all management, labor, materials, equipment, tools, and appurtenances necessary to complete the demolition of all buildings and foundations on the sites to include all electrical supply, water supply piping, drain and sewer piping, erosion control and tree protection. Remove and dump all construction demolition debris. Abatement of asbestos and lead base paint materials is to be conducted prior to demolitions. The sites will be graded, and all excavated areas filled in and lev...