Department
Public Works
Requested Action (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title
Request approval to renew an existing contract - Department of Public Works, 21ITB000003A-CJC, Water Quality Monitoring in the amount of $100,512.00 with Integrated Science Engineering, Inc. (Newman, GA), to provide water quality monitoring services. This action exercises the second of two renewal options. No renewal option remains. Effective dates: January 1, 2023, through December 31, 2023. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)
body
Requirement for Board Action (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Section 102-394(6), the Purchasing Department shall present all renewal requests to the Board of Commissioners at least 90 days prior to the contract renewal date or 60 days if the contract term is six (6) months or less.
Strategic Priority Area related to this item (If yes, note strategic priority area below)
Health and Human Services
Commission Districts Affected
All Districts ☐
District 1 ☒
District 2 ☒
District 3 ☒
District 4 ☐
District 5 ☒
District 6 ☒
Is this a purchasing item?
Yes
Summary & Background: The Department of Public Works recommends approval to renew existing contract with Integrated Science Engineering, Inc. to provide water quality monitoring services.
Scope of Work: This contract with Integrated Science Engineering, Inc. provides water quality monitoring and related services necessary to comply with Fulton County's National Pollution Discharge Elimination System (NPDES) Permits for Wastewater Treatment, which require water quality monitoring in support of the Watershed Protection Plan. The scope of work includes in-stream water quality monitoring and the collection of samples for laboratory analysis. The data collected must be submitted to the state Environmental Protection Division by June 15th of each year for the County to remain in permit compliance with the State of Georgia.
Community Impact: Water quality monitoring provides the necessary data to determine if Fulton County’s efforts to reduce pollution in the receiving streams and rivers are effective. This data is provided to the State of Georgia to assist in developing the capacity of receiving streams to accept treated water discharges.
Department Recommendation: The Department request approval to renew existing contract with Integrated Science Engineering, Inc.
Project Implications: Water quality monitoring is a regulatory requirement of the County’s National Pollution Discharge Elimination System (NPDES) Municipal Separate Storm Sewer System (MS4) permits and wastewater discharge permits. Without this contractual service, the program would be negatively impacted and could place the County in violation of the provisions of these permits, which could expose the County to fines and possible criminal prosecution.
Community Issues/Concerns: No issues/concerns were raised by clients concerning the water quality monitoring services.
Department Issues/Concerns: Public Works does not have any issues/concerns regarding the award of this contract.
Contract Modification
Current Contract History |
BOC Item |
Date |
Dollar Amount |
Original Award Amount |
21-0217 |
3/17/2021 |
$100,512.00 |
1st Renewal |
21-0938 |
12/1/2021 |
$120,000.00 |
2nd Renewal |
|
|
$100,512.00 |
Total Revised Amount |
|
|
$321,024.00 |
Contract & Compliance Information (Provide Contractor and Subcontractor details.)
Contract Value: $100,512.00
Prime Vendor: Integrated Science Engineering, Inc.
Prime Status: Non-Minority
Location: Newman, GA
County: Coweta County
Prime Value: $54,276.48 or 54.00%
Subcontractor: Analytical Environmental Services, Inc.
Subcontractor Status: White Female Business Enterprise - Certified
Location: Atlanta, GA
County: Fulton County
Contract Value: $46,235.52 or 46.00%
Subcontractor: CCR Environmental Inc.
Sub Status: Non-Minority
Location: Atlanta, GA
County: Fulton County
Subcontract Value: $TBD
Total Contract Value: $100,512.00 or 100%
Total M/FBE Value: $46,235.52 or 46.00%
Exhibits Attached
Exhibit 1: Contract Renewal Agreement
Exhibit 2: Contract Evaluation Form
Exhibit 3: Contractor Performance Report
Contact Information (Type Name, Title, Agency and Phone)
title
Roy Barnes, Deputy Director, Public Works, 404-612-6317
Contract Attached
title
No
Previous Contracts
title
Yes
Total Contract Value
Original Approved Amount: |
$220,512.00 |
Previous Adjustments: |
$0.00 |
This Request: |
$100,512.00 |
TOTAL: |
$321,024.00 |
Grant Information Summary
Amount Requested: |
|
☐ |
Cash |
Match Required: |
|
☐ |
In-Kind |
Start Date: |
|
☐ |
Approval to Award |
End Date: |
|
☐ |
Apply & Accept |
Match Account $: |
|
|
|
Fiscal Impact / Funding Source
Funding Line 1:
201-540-5420-1160: Water & Sewer Revenue, Public Works, Professional Services - $100,512.00
Key Contract Terms |
Start Date: 1/1/2023 |
End Date: 12/31/2023 |
Cost Adjustment: |
Renewal/Extension Terms: No options remain |
Overall Contractor Performance Rating: 3.60
Would you select/recommend this vendor again?
Yes
Report Period Start: |
Report Period End: |
7/1/2022 |
9/30/2022 |