DEPARTMENT
Real Estate and Asset Management
REQUESTED ACTION (Identify appropriate Action or Motion, purpose, cost, timeframe, etc.)
title
Request approval of a change order less than 10% - Department of Real Estate and Asset Management, 21RFP22421K-DB, Construction Management at Risk Services for the New Fulton County Animal Shelter Facility in the total amount of $2,823,544.00 with Winter Johnson Group (Atlanta, GA), a joint venture comprised of The Winter Construction Company and Johnson Construction Services, to modify existing contract for additional funding due to substantial costs attributable to price escalation for equipment, materials and supplies, scope changes required by regulatory agencies during permitting processes, and unforeseen conditions of developing a raw site for the new construction project for the Fulton County Animal Shelter Facility (FCAS). Effective upon BOC approval. (APPROVED)
ITEM REMOVED FROM THE CONSENT AGENDA FOR SEPARATE CONSIDERATION AS REQUESTED BY COMMISSIONER ELLIS
body
REQUIREMENT FOR BOARD ACTION (Cite specific Board policy, statute or code requirement)
In accordance with Purchasing Code Section 102-420, contract modifications within the scope of the contract and necessary for contract completion of the contract, in the specifications, services, time of performance or terms and conditions of the contract shall be forwarded to the Board of Commissioners for approval.
STRATEGIC PRIORITY AREA RELATED TO THIS ITEM (If yes, note strategic priority area below)
Open and Responsible Government
COMMISSION DISTRICTS AFFECTED
All Districts ?
District 1 ?
District 2 ?
District 3 ?
District 4 ?
District 5 ?
District 6 ?
IS THIS A PURCHASING ITEM?
Yes
SUMMARY & BACKGROUND Request approval of Change Order No. 1 for Construction Management at Risk Services modify existing contract for additional funding due to substantial costs attributable price escalation associated with the construction process for the new 58,000 sq. ft. Fu...
Click here for full text